5912 W PICKFORD ST 90035

Certificate Information: 5912 W PICKFORD ST 90035

Application / Permit
23016-10000-31857
Plan Check / Job No.
B23LA17426
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 2-CAR GARAGE TO ADU AND ADDIITON OF 2ND STORY MEZZ. PER LAMC 12.22A.33(c)-(d).
Permit Issued
Issued on 4/24/2024
Issuing Office
West Los Angeles
Current Status
Issued on 4/24/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/18/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 VIVIAN LAO
Corrections Issued 10/5/2023 VIVIAN LAO
Quality Review Completed 10/6/2023 KEN GILL
Plan Check Approved 12/11/2023 VIVIAN LAO
Issued 4/24/2024 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/23/2023 JUSTIN BICOL
Address approval Cleared 10/25/2023 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 11/7/2023 JUSTIN BICOL
Sewer availability Cleared 11/7/2023 JUSTIN BICOL

Contact Information

Architect Scrafano,, Elissa F; Lic. No.: C26071 163 N SYCAMORE      LOS ANGELES, CA 90036
Contractor Big Boy Builders Inc; Lic. No.: 1053515-B 200 S BARRINGTON AVE #491722      LOS ANGELES, CA 90049
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/25/2024 No Access for Inspection RICHARD DOCKUS
Deputy Drilled-In Anchors 4/29/2024 Conditional Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 4/29/2024 Partial Approval ALIZAH MAYAGOITIA
Sewer 4/29/2024 Approved ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 4/30/2024 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/17/2024 Partial Approval ALIZAH MAYAGOITIA
METHANE-Barrier 5/17/2024 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 5/17/2024 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 5/24/2024 Corrections Issued ARTHUR NEGRETE
Deputy Drilled-In Anchors 5/29/2024 Conditional Approval RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 5/29/2024 Approved ARTHUR NEGRETE
Wood Frame 7/2/2024 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 7/12/2024 Not Ready for Inspection ARTHUR NEGRETE
Shower Pan 7/16/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 7/18/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 7/30/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 7/30/2024 Approved ARTHUR NEGRETE
Insulation 8/1/2024 Approved ARTHUR NEGRETE
Drywall Nailing 8/7/2024 Partial Approval ANTHONY RAMOS
Green Building Rough 8/7/2024 Partial Approval ANTHONY RAMOS
BUILDING-Rough-Frame 2/27/2025 Approved ARTHUR NEGRETE
Drywall Nailing 2/27/2025 Approved ARTHUR NEGRETE
Final 2/27/2025 Corrections Issued ARTHUR NEGRETE
Footing/Foundation/Slab 2/27/2025 Approved ARTHUR NEGRETE
Green Building Final 2/27/2025 Not Ready for Inspection ARTHUR NEGRETE
Green Building Rough 2/27/2025 Approved ARTHUR NEGRETE
METHANE-Final 2/27/2025 Approved ARTHUR NEGRETE
METHANE-Rough 2/27/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 2/27/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 2/27/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Final 3/6/2025 Approved ARTHUR NEGRETE
Green Building Final 3/6/2025 Approved ARTHUR NEGRETE
Final 3/10/2025 Partial Approval ARTHUR NEGRETE
HVAC-Final 3/10/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 3/10/2025 Approved ARTHUR NEGRETE
Special/Order Compliance 3/10/2025 Partial Inspection ALEX COLIN