380 WORLD WAY TBD 90045
Certificate Information: 380 WORLD WAY TBD 90045
- Application / Permit
- 23016-10000-31815
- Plan Check / Job No.
- B23LA17406
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (3) Airport Building
- Work Description
- **ePlan**LAX TOM BRADLEY TERMINAL PROJECT ** TI in existing retail space on Level 4, suite# tbd, in DFS (Duty Free Store). Addition of a new demising wall for new tenant. Soft interior demolition, new non structural partitions, fixtures, equipment. No change of use, no structural, no change in area.
- Permit Issued
- Issued on 8/28/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/26/2025
Permit Application Status History
| Submitted | 9/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2023 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 9/24/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/10/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/15/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 7/16/2024 | FARSHAD ALIMOHAMADI |
| Issued | 8/28/2024 | APPLICANT |
| Permit Finaled | 6/25/2025 | NICK LAROCCA |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 10/6/2023 | FARSHAD ALIMOHAMADI |
| Airport buildings | Cleared | 12/15/2023 | ANDREW KO |
| Food establishment approval | Cleared | 7/16/2024 | LACDHS APPROVED |
Contact Information
| Architect | Valerio,, Niccolo; Lic. No.: NA24228 | , |
| Contractor | Premier Interior Development Inc; Lic. No.: 630171-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/24/2025 | Approved | ALAN NOVAK |
| T-Bar Ceiling | 2/24/2025 | Approved | ALAN NOVAK |
| Insulation | 2/25/2025 | Approved | ALAN NOVAK |
| Deputy Drilled-In Anchors | 3/12/2025 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 3/13/2025 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 3/14/2025 | Conditional Approval | ALAN NOVAK |
| Deputy Steel/Welding | 3/18/2025 | Partial Approval | ALAN NOVAK |
| Deputy Steel/Welding | 5/19/2025 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 5/20/2025 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 5/21/2025 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 5/22/2025 | Approved | NICK LAROCCA |
| Final | 6/25/2025 | Permit Finaled | NICK LAROCCA |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Approved | NICK LAROCCA |
| Smoke Detectors | 6/25/2025 | Approved | NICK LAROCCA |