3525-3527 N BERRY DR 91604

Certificate Information: 3525-3527 N BERRY DR 91604

Application / Permit
23016-10000-31390
Plan Check / Job No.
B23LA17181
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan convert existing 2-car garage with an office portion of (E) SFD to an ADU. ATTACHED ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 2/7/2024
Issuing Office
Current Status
CofO Issued on 12/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 ADRIANA LOPEZ
Corrections Issued 9/23/2023 ADRIANA LOPEZ
Quality Review Completed 10/11/2023 FARUK SEZER
Plan Check Approved 2/7/2024 ADRIANA LOPEZ
Issued 2/7/2024 APPLICANT
CofO in Progress 11/14/2024 CHRISTOPHE COCHRAN
Permit Finaled 12/4/2024 RUBEN SALAS
CofO Issued 12/4/2024 RUBEN SALAS
Permit Finaled 12/4/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/26/2023 COLIN LOREDO
Sewer availability Cleared 10/26/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/30/2023 COLIN LOREDO
Grading Pre-Inspection Cleared 10/31/2023 MICHAEL TEMPLE
Hydrant and Access approval Cleared 11/1/2023 LAVEON RIDER
Miscellaneous Cleared 1/4/2024 JAZMIN ROQUE
Miscellaneous Cleared 1/4/2024 JAZMIN ROQUE
Specific Plan Cleared 1/17/2024 TIFFANY CORRALES

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/8/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 5/8/2024 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/8/2024 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 5/8/2024 Partial Approval CHRISTOPHE COCHRAN
Underground Mechanical 5/8/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/28/2024 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 5/28/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 5/28/2024 Approved CHRISTOPHE COCHRAN
HVAC-Rough 5/28/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 5/28/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 6/6/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Rough-Elec/Plmb/HVAC 6/6/2024 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 6/7/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 6/11/2024 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 6/20/2024 Approved CHRISTOPHE COCHRAN
Insulation 7/3/2024 Corrections Issued CHRISTOPHE COCHRAN
Interior/Exterior Lathing 7/3/2024 Approved CHRISTOPHE COCHRAN
Insulation 7/12/2024 Approved RYAN SALAZAR
Drywall Nailing 8/7/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Not Ready CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/14/2024 Approved CHRISTOPHE COCHRAN
Final 11/14/2024 OK to Issue CofO CHRISTOPHE COCHRAN
Green Building Final 11/14/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 11/14/2024 Approved CHRISTOPHE COCHRAN