5819 W GREGORY AVE 90038

Certificate Information: 5819 W GREGORY AVE 90038

Application / Permit
23016-10000-31193
Plan Check / Job No.
B23LA17116
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
MAINTENANCE, REPAIRS, AND REHABILITATION OF (E) 16-UNIT APT BLDG AND (N) ROOFING
Permit Issued
Issued on 10/17/2024
Issuing Office
Current Status
Permit Finaled on 6/3/2026

Permit Application Status History

Submitted 9/19/2023 APPLICANT
Assigned to Plan Check Engineer 9/21/2023 SEAN SHAHMIRI
Corrections Issued 9/25/2023 SEAN SHAHMIRI
Quality Review Completed 10/3/2023 OMID HEDAYAT
Plan Check Approved 2/29/2024 SEAN SHAHMIRI
Issued 10/17/2024 APPLICANT
Permit Finaled 6/1/2026 REGINA MENDEZ

Permit Application Clearance Information

DAS Clearance Cleared 12/20/2023 Shangqin Xie
Public Housing Cleared 12/20/2023 LUIS ALVAREZ
Green Code Cleared 12/21/2023 Shangqin Xie
Fire Marshal Fire Life Safety Cleared 2/24/2024 FIRE DEPARTMENT
Tenant Habitability Plan Cleared 10/16/2024 RICARDO BOHORQUEZ

Contact Information

Architect Egan,, John S; Lic. No.: C28572 EGAN SIMON ARCHITECTURE   7740 W. MANCHESTER AVE. STE. 205    PLAYA DEL REY, CA 90293
Contractor Ibca Llc; Lic. No.: 1112873-B       ,
Contractor Icon Builders; Lic. No.: 1112873-B       ,
Engineer Garcia,, Lionel J; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/20/2025 Not Ready for Inspection TIMOTHY POWELL
Wall Anchors 5/20/2025 Not Ready for Inspection TIMOTHY POWELL
Footing/Foundation/Slab 5/27/2025 Partial Approval PAUL BAZERKANIAN
Wall Anchors 5/27/2025 Partial Approval PAUL BAZERKANIAN
Wood Frame 5/27/2025 Partial Approval PAUL BAZERKANIAN
Wood Frame 6/4/2025 Partial Approval TIMOTHY POWELL
Drywall Nailing 6/5/2025 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 6/5/2025 Corrections Issued TIMOTHY POWELL
Drywall Nailing 6/9/2025 Partial Inspection TIMOTHY POWELL
Drywall Nailing 6/11/2025 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 6/12/2025 Partial Approval TIMOTHY POWELL
Interior/Exterior Lathing 6/16/2025 Partial Approval TIMOTHY POWELL
Interior/Exterior Lathing 6/18/2025 Not Ready for Inspection TIMOTHY POWELL
Wood Frame 6/18/2025 Partial Approval TIMOTHY POWELL
Special/Order Compliance 6/26/2025 Partial Inspection TIMOTHY POWELL
Wood Frame 6/27/2025 Approved MARTIN TAVITIAN
Drywall Nailing 6/30/2025 Partial Approval PAUL BAZERKANIAN
Green Building Final 1/13/2026 Not Ready for Inspection LUIS CCAMACHO
METHANE-Final 1/13/2026 Not Ready for Inspection LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Not Ready LUIS CCAMACHO
Smoke Detectors 1/13/2026 Not Ready for Inspection LUIS CCAMACHO
Final 4/28/2026 Not Ready for Inspection LUIS CCAMACHO
Green Building Final 4/28/2026 Approved LUIS CCAMACHO
METHANE-Final 4/28/2026 Approved LUIS CCAMACHO
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Approved LUIS CCAMACHO
Smoke Detectors 4/28/2026 Approved LUIS CCAMACHO
Final 5/21/2026 Not Ready for Inspection REGINA MENDEZ
Final 6/1/2026 Permit Finaled REGINA MENDEZ