4188 S HARVARD BLVD 90062
Certificate Information: 4188 S HARVARD BLVD 90062
- Application / Permit
- 23016-10000-30940
- Plan Check / Job No.
- B23LA16984
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 22'-0" X 13'-0" DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER WFPP AND ENGINEER DETAIL.
- Permit Issued
- Issued on 1/4/2024
- Issuing Office
- Current Status
- CofO Issued on 7/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 9/16/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 12/21/2023 | MADISON ODELL |
| Plan Check Approved | 1/3/2024 | MADISON O'DELL |
| Issued | 1/4/2024 | APPLICANT |
| CofO in Progress | 7/9/2024 | SABAS ALONSO |
| Permit Finaled | 7/10/2024 | DEROLD HAUFF |
| CofO Issued | 7/10/2024 | DEROLD HAUFF |
| Permit Finaled | 7/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/26/2023 | AMBER CAMPBELL |
| Sewer availability | Cleared | 9/26/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 9/28/2023 | AMBER CAMPBELL |
| Construction near power lines | Cleared | 12/12/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pulido,, Jose Luis; Lic. No.: C75631 | 9131 COLLETT AVENUE NORTH HILLS, CA 91343 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/7/2024 | Corrections Issued | SABAS ALONSO |
| Footing/Foundation/Slab | 3/18/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 3/27/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 4/8/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 4/8/2024 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 4/8/2024 | Approved | SABAS ALONSO |
| Sewer | 4/8/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/8/2024 | Approved | SABAS ALONSO |
| Insulation | 4/15/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/23/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/23/2024 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 4/29/2024 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 5/3/2024 | Approved | SABAS ALONSO |
| Final | 5/16/2024 | Corrections Issued | SABAS ALONSO |
| Gas Test | 5/16/2024 | Approved | SABAS ALONSO |
| Pre-Inspection | 5/20/2024 | No Access for Inspection | SABAS ALONSO |
| Pre-Inspection | 5/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/7/2024 | Approved | SABAS ALONSO |
| Final | 6/7/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 6/7/2024 | Approved | SABAS ALONSO |
| Smoke Detectors | 6/7/2024 | Approved | SABAS ALONSO |
| Final | 6/11/2024 | Corrections Issued | ANTHONY EGSON |
| Final | 6/25/2024 | Corrections Issued | SABAS ALONSO |
| Final | 7/8/2024 | OK to Issue CofO | SABAS ALONSO |