422 W 110TH ST 90061
Certificate Information: 422 W 110TH ST 90061
- Application / Permit
- 23016-10000-30903
- Plan Check / Job No.
- B23LA16965
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Current Status
- CofO Issued on 11/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 9/16/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 12/6/2023 | ALEC MOUSAKHANIAN |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 11/19/2024 | BEN MOLSTAD |
| Permit Finaled | 11/21/2024 | ANSON MAGLASANG |
| CofO Issued | 11/21/2024 | ANSON MAGLASANG |
| Permit Finaled | 11/21/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2023 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/2/2023 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2023 | JUSTIN BICOL |
| Sewer availability | Cleared | 10/25/2023 | JUSTIN BICOL |
| Tenant Habitability Plan | Cleared | 11/2/2023 | RICARDO BOHORQUEZ |
| Construction near power lines | Cleared | 11/16/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/16/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xi,, Wang; Lic. No.: NA85148 | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/21/2024 | Corrections Issued | JAMES CHAVEZ |
| Sewer | 3/21/2024 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 5/23/2024 | Corrections Issued | JAMES CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 5/29/2024 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Partial Approval | JAMES CHAVEZ |
| Special/Order Compliance | 6/26/2024 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 8/5/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 8/5/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 8/5/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 8/5/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/29/2024 | Partial Approval | BARRY HACHE |
| Insulation | 8/29/2024 | Approved | BARRY HACHE |
| Interior/Exterior Lathing | 8/29/2024 | Approved | BARRY HACHE |
| Shower Pan | 8/29/2024 | Approved | BARRY HACHE |
| Drywall Nailing | 9/6/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 10/11/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 10/11/2024 | Corrections Issued | BARRY HACHE |
| Final | 10/11/2024 | Not Ready for Inspection | BARRY HACHE |
| Green Building Final | 10/11/2024 | Corrections Issued | BARRY HACHE |
| Green Building Rough | 10/11/2024 | Approved | BARRY HACHE |
| HVAC-Final | 10/11/2024 | Approved | BARRY HACHE |
| MERV13>=Final | 10/11/2024 | Approved | BARRY HACHE |
| MERV13>=Rough | 10/11/2024 | Approved | BARRY HACHE |
| PLUMBING-Final | 10/11/2024 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 10/11/2024 | SGSOV Approved | BARRY HACHE |
| Service/Power Release | 10/11/2024 | Not Ready for Inspection | BARRY HACHE |
| Smoke Detectors | 10/11/2024 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 10/18/2024 | Approved | BEN MOLSTAD |
| Final | 10/18/2024 | Corrections Issued | BEN MOLSTAD |
| Gas Test | 10/18/2024 | Approved | BEN MOLSTAD |
| Green Building Final | 10/18/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 10/18/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 10/18/2024 | Approved | BEN MOLSTAD |
| Final | 11/19/2024 | OK to Issue CofO | BEN MOLSTAD |