422 W 110TH ST 90061

Certificate Information: 422 W 110TH ST 90061

Application / Permit
23016-10000-30903
Plan Check / Job No.
B23LA16965
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 1/23/2024
Issuing Office
Current Status
CofO Issued on 11/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2023 APPLICANT
Assigned to Plan Check Engineer 9/15/2023 ALEC MOUSAKHANIAN
Corrections Issued 9/16/2023 ALEC MOUSAKHANIAN
Plan Check Approved 12/6/2023 ALEC MOUSAKHANIAN
Issued 1/23/2024 APPLICANT
CofO in Progress 11/19/2024 BEN MOLSTAD
Permit Finaled 11/21/2024 ANSON MAGLASANG
CofO Issued 11/21/2024 ANSON MAGLASANG
Permit Finaled 11/21/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/2/2023 STEVE MELGAR
Roof/Waste drainage to street Cleared 10/2/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/3/2023 JUSTIN BICOL
Sewer availability Cleared 10/25/2023 JUSTIN BICOL
Tenant Habitability Plan Cleared 11/2/2023 RICARDO BOHORQUEZ
Construction near power lines Cleared 11/16/2023 RIDWAN HARDY
Construction within easement Cleared 11/16/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Xi,, Wang; Lic. No.: NA85148       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/21/2024 Corrections Issued JAMES CHAVEZ
Sewer 3/21/2024 Approved JAMES CHAVEZ
Footing/Foundation/Slab 5/23/2024 Corrections Issued JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 5/29/2024 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Partial Approval JAMES CHAVEZ
Special/Order Compliance 6/26/2024 Corrections Issued JAMES CHAVEZ
BUILDING-Rough-Frame 8/5/2024 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 8/5/2024 Approved JOSEPH MCGARRY
HVAC-Rough 8/5/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 8/5/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 8/29/2024 Partial Approval BARRY HACHE
Insulation 8/29/2024 Approved BARRY HACHE
Interior/Exterior Lathing 8/29/2024 Approved BARRY HACHE
Shower Pan 8/29/2024 Approved BARRY HACHE
Drywall Nailing 9/6/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 10/11/2024 Approved BARRY HACHE
ELECTRICAL-Final 10/11/2024 Corrections Issued BARRY HACHE
Final 10/11/2024 Not Ready for Inspection BARRY HACHE
Green Building Final 10/11/2024 Corrections Issued BARRY HACHE
Green Building Rough 10/11/2024 Approved BARRY HACHE
HVAC-Final 10/11/2024 Approved BARRY HACHE
MERV13>=Final 10/11/2024 Approved BARRY HACHE
MERV13>=Rough 10/11/2024 Approved BARRY HACHE
PLUMBING-Final 10/11/2024 Corrections Issued BARRY HACHE
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Approved BARRY HACHE
Service/Power Release 10/11/2024 Not Ready for Inspection BARRY HACHE
Smoke Detectors 10/11/2024 Approved BARRY HACHE
ELECTRICAL-Final 10/18/2024 Approved BEN MOLSTAD
Final 10/18/2024 Corrections Issued BEN MOLSTAD
Gas Test 10/18/2024 Approved BEN MOLSTAD
Green Building Final 10/18/2024 Approved BEN MOLSTAD
PLUMBING-Final 10/18/2024 Approved BEN MOLSTAD
Service/Power Release 10/18/2024 Approved BEN MOLSTAD
Final 11/19/2024 OK to Issue CofO BEN MOLSTAD