1505 E 109TH ST 90059
Certificate Information: 1505 E 109TH ST 90059
- Application / Permit
- 23016-10000-30888
- Plan Check / Job No.
- B23LA16948
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Current Status
- CofO Issued on 10/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2023 | ALFREDO JARA |
| Corrections Issued | 9/30/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 10/22/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 12/21/2023 | GURUNATH NESARAJAH |
| Plan Check Approved | 4/22/2024 | GURUNATH NESARAJAH |
| Issued | 6/6/2024 | APPLICANT |
| CofO in Progress | 10/9/2025 | ANTHONY EGSON |
| CofO in Progress | 10/20/2025 | ANTHONY EGSON |
| CofO in Progress | 10/30/2025 | ANTHONY EGSON |
| Permit Finaled | 10/30/2025 | ANSON MAGLASANG |
| CofO Issued | 10/30/2025 | ANSON MAGLASANG |
| Permit Finaled | 10/30/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/10/2023 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 10/16/2023 | ARNULFO CHAMU |
| Roof/Waste drainage to street | Cleared | 10/16/2023 | ARNULFO CHAMU |
| Sewer availability | Cleared | 10/16/2023 | ARNULFO CHAMU |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2023 | ARNULFO CHAMU |
| ZI | Cleared | 10/27/2023 | NELSON RODRIGUEZ |
Contact Information
| Contractor | Leslie Electric Co; Lic. No.: 936228-B | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/13/2024 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 7/3/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Footing/Foundation/Slab | 7/8/2024 | Corrections Issued | ANSON MAGLASANG |
| Footing/Foundation/Slab | 7/16/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/13/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/2/2024 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 12/20/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/20/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 12/20/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/15/2025 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 1/15/2025 | Partial Approval | ANTHONY EGSON |
| ELECTRICAL-Rough | 1/22/2025 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/28/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/4/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 2/4/2025 | Approved | ANTHONY EGSON |
| HVAC-Rough | 2/4/2025 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 2/4/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 2/4/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 2/6/2025 | Approved | ANTHONY EGSON |
| Insulation | 2/12/2025 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 2/25/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/25/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/2/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 6/2/2025 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 6/2/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 6/2/2025 | Approved | BEN MOLSTAD |
| Final | 7/17/2025 | Corrections Issued | JOHN KLARIN |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Approved | JOHN KLARIN |
| Final | 7/28/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 8/14/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 8/20/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 8/25/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 9/3/2025 | Corrections Issued | ANTHONY EGSON |
| Final | 9/3/2025 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 9/24/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 10/6/2025 | Approved | ANTHONY EGSON |
| Final | 10/8/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 10/8/2025 | Approved | ANTHONY EGSON |
| Final | 10/29/2025 | OK to Issue CofO | ANTHONY EGSON |