10381 W MISSISSIPPI AVE 90025
Certificate Information: 10381 W MISSISSIPPI AVE 90025
- Application / Permit
- 23016-10000-30859
- Plan Check / Job No.
- B23LA16929
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- REBUILD EXISTING GARAGE, SAME FOOTPRINT (284 SQFT)
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 4/16/2025
Permit Application Status History
| Submitted | 9/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | NGHI SU |
| Corrections Issued | 9/27/2023 | NGHI SU |
| Quality Review Completed | 9/29/2023 | KEN GILL |
| Building Plans Picked Up | 10/24/2023 | APPLICANT |
| Applicant returned to address corrections | 3/15/2024 | NGHI SU |
| Plan Check Approved | 4/30/2024 | NGHI SU |
| Issued | 5/30/2024 | APPLICANT |
| Permit Finaled | 4/15/2025 | DANIEL VERA |
Permit Application Clearance Information
| ZA Case | Cleared | 11/2/2023 | MAYELA VILLA |
| Roof/Waste drainage to street | Cleared | 2/6/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2024 | DARIN LAM |
| Grading Pre-Inspection | Cleared | 3/15/2024 | NGHI SU |
Contact Information
| Contractor | Elemental Design Inc; Lic. No.: 897423-B | 3038 HILLCREST DRIVE LOS ANGELES, CA 900164101 |
| Engineer | Lombera,, Raymundo Alcaraz; Lic. No.: L7740 | 135 S JACKSON STREET #202 GLENDALE, CA 91205 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
| Geologist | Gladson,, Richard Arthur; Lic. No.: EG1758 | 1545 VICTORY BL 2ND FLOOR GLENDALE, CA 91201 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/9/2024 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 9/19/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/19/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Piling/Pier/Caisson | 9/19/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 9/24/2024 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/24/2024 | Partial Approval | STEPHANIE SWANSON |
| Piling/Pier/Caisson | 9/24/2024 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 9/27/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/27/2024 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/30/2024 | Partial Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 10/15/2024 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/15/2024 | Approved | STEPHANIE SWANSON |
| Reinforced Concrete Frame | 10/15/2024 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/31/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2024 | Approved | STEPHANIE SWANSON |
| Wood Frame | 12/12/2024 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/20/2024 | Conditional Approval | STEPHANIE SWANSON |
| Insulation | 12/31/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Insulation | 1/16/2025 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 1/28/2025 | Approved | STEPHANIE SWANSON |
| Final | 4/15/2025 | Permit Finaled | DANIEL VERA |
| METHANE-Final | 4/15/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 4/15/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 4/15/2025 | Approved | DANIEL VERA |