2663 W AVENUE 35 90065
Certificate Information: 2663 W AVENUE 35 90065
- Application / Permit
- 23016-10000-30764
- Plan Check / Job No.
- B23LA16864
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 11/14/2023
- Issuing Office
- Current Status
- CofO Issued on 7/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2023 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 9/18/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 11/1/2023 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 11/5/2023 | MOHAMMAD ESMAILI |
| No Progress | 11/9/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/9/2023 | MOHAMMAD ESMAILI |
| Issued | 11/14/2023 | APPLICANT |
| CofO in Progress | 7/24/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 7/25/2025 | DEROLD HAUFF |
| CofO Issued | 7/25/2025 | DEROLD HAUFF |
| Permit Finaled | 7/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/19/2023 | NEIL TUANO |
| Sewer availability | Cleared | 9/19/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2023 | NEIL TUANO |
| Specific Plan | Cleared | 9/29/2023 | ANDREA MAGANA-WITHERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: C76425 | 641 S ALMIRANTE DR WEST COVINA, CA 91791 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/26/2024 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/30/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 4/30/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/24/2024 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 5/24/2024 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 6/21/2024 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 9/10/2024 | Partial Approval | ROY SPAULDING |
| PLUMBING-Rough | 9/10/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/26/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 9/26/2024 | Approved | THOMAS LOGRASSO |
| Deputy Wood Construction | 9/27/2024 | Conditional Approval | THOMAS LOGRASSO |
| HVAC-Rough | 10/24/2024 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 10/29/2024 | Corrections Issued | ROY SPAULDING |
| Wood Frame | 10/29/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 12/3/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/19/2024 | Conditional Approval | THOMAS LOGRASSO |
| Shower Pan | 12/19/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 1/13/2025 | Conditional Approval | THOMAS LOGRASSO |
| Drywall Nailing | 1/27/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 2/19/2025 | Partial Approval | THOMAS LOGRASSO |
| Final | 6/27/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 6/27/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 6/27/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 7/16/2025 | Corrections Issued | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 7/16/2025 | Approved | NICHOLAS LOPEZ |
| Final | 7/23/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/23/2025 | SGSOV Approved | NICHOLAS LOPEZ |