105-107 E NAPOLEON ST 90293
Certificate Information: 105-107 E NAPOLEON ST 90293
- Application / Permit
- 23016-10000-30762
- Plan Check / Job No.
- B23LA16863
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan PROPOSED INTERIOR REMODELING TO (E) DUPLEX CONSISTING OF INCLOSING DOOR OEPINING BETWEEN TWO UNITS BY 1 HOUR RATED WALL AND PROVIDING NEW SPEARATE ENTRY FOR UNIT 105 NAPOLEON. NO PROPOSED CHANGE IN RFA, HEIGHT OR DIMENSION OF (E) STRUCTURE "COMPLY WITH DEPARTMENT ORDER effective date 04/01/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 1/12/2024
- Issuing Office
- Current Status
- Permit Finaled on 3/28/2024
Permit Application Status History
| Submitted | 9/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2023 | JAD BASMA |
| Corrections Issued | 9/28/2023 | JAD BASMA |
| Quality Review Completed | 10/2/2023 | GARO TELMI |
| Applicant returned to address corrections | 10/20/2023 | JAD BASMA |
| Plan Check Approved | 10/31/2023 | JAD BASMA |
| Plan Check Approved | 1/12/2024 | JAD BASMA |
| No Progress | 1/12/2024 | JAD BASMA |
| Plan Check Approved | 1/12/2024 | JAD BASMA |
| Issued | 1/12/2024 | APPLICANT |
| Permit Finaled | 3/28/2024 | ANDREW BEELI |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/31/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Dhs Ventures Inc; Lic. No.: 1047699-B | , |
| Contractor | La Ccs; Lic. No.: 1047699-B | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 1/17/2024 | Not Ready for Inspection | ANDREW BEELI |
| Wood Frame | 1/17/2024 | Corrections Issued | ANDREW BEELI |
| Drywall Nailing | 1/19/2024 | Not Ready for Inspection | ANDREW BEELI |
| Insulation | 1/19/2024 | Approved | ANDREW BEELI |
| Special/Order Compliance | 1/19/2024 | Corrections Issued | ANDREW BEELI |
| Wood Frame | 1/19/2024 | Approved | ANDREW BEELI |
| Drywall Nailing | 1/24/2024 | Partial Approval | ANDREW BEELI |
| Final | 2/9/2024 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 2/9/2024 | SGSOV Approved | ANDREW BEELI |
| Smoke Detectors | 2/9/2024 | Not Ready for Inspection | ANDREW BEELI |
| Final | 3/28/2024 | Permit Finaled | ANDREW BEELI |
| Smoke Detectors | 3/28/2024 | Approved | ANDREW BEELI |