4 S BEVERLY PARK 90210
Certificate Information: 4 S BEVERLY PARK 90210
- Application / Permit
- 23016-10000-30600
- Plan Check / Job No.
- B23LA16789
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (22) Storage Building
- Work Description
- PROPOSED UNDER EXISTING CONCRETE DECK - STORAGE ROOM (450 SQFT) AND PASSAGEWAY.
- Permit Issued
- Issued on 2/2/2024
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 10/2/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/4/2023 | KEN GILL |
| Building Plans Picked Up | 10/6/2023 | APPLICANT |
| Plan Check Approved | 2/2/2024 | ARSALAN SHABESTARI |
| Issued | 2/2/2024 | APPLICANT |
| CofO in Progress | 8/22/2024 | SEAN HAUPT |
| Permit Finaled | 8/26/2024 | RICHARD STEINBACH |
| CofO Issued | 8/26/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/26/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 10/24/2023 | DALIA MOKAYED |
| Roof/Waste drainage to street | Cleared | 10/27/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 11/8/2023 | ANDREA SAINT-ANTONIN |
| ZI | Cleared | 11/20/2023 | DAVID URITA |
| ZI | Cleared | 11/20/2023 | DAVID URITA |
| Grading Pre-Inspection | Cleared | 12/7/2023 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Cm Construction Inc; Lic. No.: 1030804-B | 9512 HILLHAVEN AVE TUJUNGA, CA 91042 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/29/2024 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 3/4/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 3/4/2024 | Partial Approval | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 7/17/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 7/19/2024 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 8/21/2024 | Approved | SEAN HAUPT |
| Final | 8/21/2024 | OK to Issue CofO | SEAN HAUPT |
| Footing/Foundation/Slab | 8/21/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 8/21/2024 | Approved | SEAN HAUPT |