1623 S BEDFORD ST 5 90035

Certificate Information: 1623 S BEDFORD ST 5 90035

Application / Permit
23016-10000-30220
Plan Check / Job No.
B23LA16573
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan. Convert (E) Attached 2-Car Garage to living space (DEN) within (E) 3-Story Multi-Family Residential Bldg. No parking required per AB 2097
Permit Issued
Issued on 11/29/2023
Issuing Office
Current Status
Permit Finaled on 5/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2023 APPLICANT
Assigned to Plan Check Engineer 9/14/2023 RACHEL BEYENE
Corrections Issued 9/19/2023 RACHEL BEYENE
Quality Review Completed 10/6/2023 HERNAN ARREOLA
Applicant returned to address corrections 11/7/2023 RACHEL BEYENE
Plan Check Approved 11/28/2023 RAHEL BEYENE
Issued 11/29/2023 APPLICANT
Permit Finaled 5/7/2024 FARHAD DADBIN

Permit Application Clearance Information

Tenant Habitability Plan Cleared 10/19/2023 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 10/23/2023 ARNULFO CHAMU
Sewer availability Cleared 10/23/2023 ARNULFO CHAMU

Contact Information

Architect Santiago-Dieppa,, Rafael Angel; Lic. No.: NA10361       ,
Contractor Owner-Builder       ,

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 1/25/2024 Not Ready for Inspection FARHAD DADBIN
Footing/Foundation/Slab 1/25/2024 Partial Approval FARHAD DADBIN
Interior/Exterior Lathing 1/25/2024 Not Ready for Inspection FARHAD DADBIN
Wood Frame 1/25/2024 Corrections Issued FARHAD DADBIN
Insulation 1/29/2024 Corrections Issued FARHAD DADBIN
Wood Frame 1/31/2024 Conditional Approval FARHAD DADBIN
Drywall Nailing 2/2/2024 Partial Approval GRANT WOODS
Interior/Exterior Lathing 2/13/2024 Approved FARHAD DADBIN
Drywall Nailing 2/20/2024 Approved FARHAD DADBIN
Interior/Exterior Lathing 2/20/2024 Approved FARHAD DADBIN
Final 4/17/2024 Partial Approval FARHAD DADBIN
METHANE-Final 4/17/2024 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Approved FARHAD DADBIN
Smoke Detectors 4/17/2024 Approved FARHAD DADBIN
Final 5/7/2024 Permit Finaled FARHAD DADBIN