7631 N LINDLEY AVE 91335
Certificate Information: 7631 N LINDLEY AVE 91335
- Application / Permit
- 23016-10000-29720
- Plan Check / Job No.
- B23LA16410
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE INTO ADU BY STATE LAW.
- Permit Issued
- Issued on 9/25/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2023 | GEORGE ALVAREZ |
| Corrections Issued | 9/10/2023 | GEORGE ALVAREZ |
| Building Plans Picked Up | 9/15/2023 | APPLICANT |
| Plan Check Approved | 9/22/2023 | NEHEMIAS RAMOS |
| Issued | 9/25/2023 | APPLICANT |
| CofO in Progress | 6/27/2024 | JEFFREY BULL |
| Permit Finaled | 7/23/2024 | JOHN JANSON |
| CofO Issued | 7/23/2024 | JOHN JANSON |
| Permit Finaled | 7/23/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/20/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/20/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/13/2023 | Corrections Issued | HENRY KIM |
| Pre-Inspection | 2/13/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 3/5/2024 | Partial Approval | JEFFREY BULL |
| Deputy Drilled-In Anchors | 3/20/2024 | Conditional Approval | JEFFREY BULL |
| Footing/Foundation/Slab | 3/21/2024 | Approved | JEFFREY BULL |
| Deputy Wood Construction | 4/18/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 4/18/2024 | Not Ready for Inspection | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 4/18/2024 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 4/18/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 4/18/2024 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 4/19/2024 | Approved | JEFFREY BULL |
| Insulation | 4/23/2024 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 4/23/2024 | Approved | JEFFREY BULL |
| Drywall Nailing | 4/25/2024 | Approved | TROY SANDERS |
| Sewer | 5/23/2024 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 5/24/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | JEFFREY BULL |
| Final | 5/31/2024 | Not Ready for Inspection | JEFFREY BULL |
| Green Building Final | 5/31/2024 | Approved | JEFFREY BULL |
| Green Building Rough | 5/31/2024 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 5/31/2024 | Approved | JEFFREY BULL |
| Smoke Detectors | 5/31/2024 | Approved | JEFFREY BULL |
| Final | 6/27/2024 | OK to Issue CofO | JEFFREY BULL |