12756 W KLING ST 91604

Certificate Information: 12756 W KLING ST 91604

Application / Permit
23016-10000-29562
Plan Check / Job No.
B23LA16322
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Interior Remodel to (E) SFD with structural renovation and removal of chimney. All work per engineered plans.
Permit Issued
Issued on 9/25/2023
Issuing Office
Current Status
Permit Finaled on 6/1/2024

Permit Application Status History

Submitted 9/1/2023 APPLICANT
Assigned to Plan Check Engineer 9/8/2023 WEIJIAN HUANG
Corrections Issued 9/11/2023 WEIJIAN HUANG
Plan Check Approved 9/25/2023 MICHAEL LANZONE
Issued 9/25/2023 APPLICANT
Permit Finaled 6/1/2024 MICHEL ABAJAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Villafana,, Donald E; Lic. No.: C37354 1050 STERN LANE      OXNARD, CA 93030

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/3/2023 Corrections Issued JUAN VALENZUELA
Deputy Drilled-In Anchors 11/7/2023 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 11/13/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 11/14/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/14/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/14/2023 Partial Approval CHRISTOPHE COCHRAN
MERV13>=Rough 11/14/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 11/14/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/17/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/17/2023 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Rough 11/22/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 11/22/2023 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 11/22/2023 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/29/2023 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/29/2023 Corrections Issued CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Insulation 11/29/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
MERV13>=Rough 11/29/2023 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 11/30/2023 Approved CHRISTOPHER ROJAS
Green Building Rough 11/30/2023 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 11/30/2023 Approved CHRISTOPHER ROJAS
Insulation 12/4/2023 Approved CHRISTOPHE COCHRAN
Deputy Wood Construction 12/5/2023 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 12/6/2023 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Approved JUAN VALENZUELA
Shower Pan 12/15/2023 Approved MICHEL ABAJAN
Drywall Nailing 12/19/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/12/2024 Partial Approval CHRISTOPHE COCHRAN
Final 5/23/2024 Corrections Issued CHRISTOPHE COCHRAN
MERV13>=Final 5/23/2024 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 5/23/2024 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 5/23/2024 Approved CHRISTOPHE COCHRAN
Final 5/31/2024 Off-Hour Fees Due
Final 6/1/2024 Off-Hour Fees Due
Final 6/1/2024 Permit Finaled MICHEL ABAJAN