1551 N LA BREA AVE 90028
Certificate Information: 1551 N LA BREA AVE 90028
- Application / Permit
- 23016-10000-29423
- Plan Check / Job No.
- B23LA16269
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- ePlan MODIFICATION TO EXISTING ROOFTOP WIRELESS SITE PER ZA-2022-6943-CUW.
- Permit Issued
- Issued on 8/19/2024
- Issuing Office
- Current Status
- Issued on 8/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2023 | MICHAEL LOPEZ |
| Corrections Issued | 9/8/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 10/20/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/14/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 2/22/2024 | KEVIN MORALES |
| Issued | 8/19/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2023 | WALLIE JONG |
| Fire Marshal Fire Life Safety | Cleared | 1/12/2024 | FIRE DEPARTMENT |
| Plan Approval | Cleared | 1/22/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 1/22/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 1/22/2024 | LESLIE PEREZ |
| ZI | Cleared | 1/24/2024 | NOAH MCCOY |
| Historic Resource Verification | Cleared | 2/1/2024 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 2/8/2024 | DAVID URITA |
Contact Information
| Architect | Do,, Dung Khac; Lic. No.: C18015 | 26 EXECUTIVE PARK SUITE 170 IRVINE, CA 92614 |
| Contractor | Procell; Lic. No.: 951819-B | , |
| Contractor | Process Cellular Inc; Lic. No.: 951819-B | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2024 | Partial Inspection | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Partial Inspection | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Partial Approval | TIMOTHY POWELL |
| Final | 1/13/2026 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 1/13/2026 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 1/13/2026 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 1/13/2026 | Not Ready for Inspection | JEFFREY FULTON |