8100 S TRUXTON AVE 90045
Certificate Information: 8100 S TRUXTON AVE 90045
- Application / Permit
- 23016-10000-29347
- Plan Check / Job No.
- B23LA16240
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel only to remove walls. All work per engineer. "COMPLY WITH DEPARTMENT ORDER effective date 05/26/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 8/30/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/29/2023
Permit Application Status History
| Plan Check Approved | 8/30/2023 | VICTOR CHEN |
| Issued | 8/30/2023 | APPLICANT |
| Permit Finaled | 9/29/2023 | ANDREW BEELI |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/8/2023 | Partial Approval | ANDREW BEELI |
| Final | 9/15/2023 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 9/15/2023 | Approved | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/15/2023 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 9/15/2023 | Not Ready for Inspection | ANDREW BEELI |
| Wood Frame | 9/15/2023 | Not Ready for Inspection | ANDREW BEELI |
| Final | 9/19/2023 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 9/19/2023 | Not Ready for Inspection | ANDREW BEELI |
| Wood Frame | 9/19/2023 | Approved | ANDREW BEELI |
| Drywall Nailing | 9/26/2023 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | ANDREW BEELI |
| Final | 9/29/2023 | Permit Finaled | ANDREW BEELI |
| Smoke Detectors | 9/29/2023 | Approved | ANDREW BEELI |