140-144 E OPP ST 90744

Certificate Information: 140-144 E OPP ST 90744

Application / Permit
23016-10000-29119
Plan Check / Job No.
B23LA16121
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN: CONVERT A PORTION OF (E) ATTACHED GARAGE UNDER (E) DUPLEX INTO A (N) IRREGULAR SHAPED 30'-2" x 21'-6" ATTACHED ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65862.2(e)(1)(C) PER ENGINEERING
Permit Issued
Issued on 10/3/2023
Issuing Office
Current Status
Issued on 10/3/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/30/2023 APPLICANT
Assigned to Plan Check Engineer 9/5/2023 ALFRED RAMIREZ
Corrections Issued 9/6/2023 ALFRED RAMIREZ
Plan Check Approved 9/27/2023 ALFRED RAMIREZ
Issued 10/3/2023 APPLICANT

Permit Application Clearance Information

"Q" conditions Cleared 9/7/2023 DAVID URITA
Address approval Cleared 9/12/2023 ERIK BEASLEY
Sewer availability Cleared 9/12/2023 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 9/18/2023 ERIK BEASLEY

Contact Information

Contractor Andrew Mark Ibrahim; Lic. No.: 1034561-B       ,
Contractor Ibrahim Andrew Mark; Lic. No.: 1034561-B       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/21/2024 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 5/3/2024 Corrections Issued EUGENE CASSIDY
Green Building Rough 5/3/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 5/3/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 6/29/2024 Corrections Issued BEN MOLSTAD
PLUMBING-Rough 6/29/2024 Corrections Issued BEN MOLSTAD
BUILDING-Rough-Frame 7/17/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 7/17/2024 Corrections Issued EUGENE CASSIDY
Green Building Rough 7/17/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 7/17/2024 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 8/5/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/5/2024 Approved EUGENE CASSIDY
Green Building Rough 8/5/2024 Approved EUGENE CASSIDY
Insulation 8/5/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 8/5/2024 Approved EUGENE CASSIDY
Deputy Wood Construction 8/9/2024 Conditional Approval BARRY HACHE
Drywall Nailing 9/19/2024 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 9/19/2024 Approved JOSEPH MCGARRY
Drywall Nailing 9/24/2024 Approved EUGENE CASSIDY