457 S MARIPOSA AVE 90020
Certificate Information: 457 S MARIPOSA AVE 90020
- Application / Permit
- 23016-10000-29077
- Plan Check / Job No.
- B23LA16087
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- Proposed Roof Deck of (E) Hotel 4th floor
- Permit Issued
- Issued on 8/17/2024
- Issuing Office
- Current Status
- Permit Finaled on 9/3/2025
Permit Application Status History
| Submitted | 8/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | HERNAN ARREOLA |
| Corrections Issued | 9/10/2023 | HERNAN ARREOLA |
| Quality Review Completed | 9/11/2023 | PETER KIM |
| Applicant returned to address corrections | 12/14/2023 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/24/2024 | HERNAN ARREOLA |
| Plan Check Approved | 7/3/2024 | HERNAN ARREOLA |
| Issued | 8/17/2024 | APPLICANT |
| Permit Finaled-Status Void | 8/27/2025 | LUIS CCAMACHO |
| Permit Finaled | 8/27/2025 | LUIS CCAMACHO |
| Re-Activate Permit | 9/3/2025 | LUIS CCAMACHO |
Permit Application Clearance Information
| ZA Case | Cleared | 4/11/2024 | YINGSHI HUANG |
| RDP Residential Hotel/SRO | Cleared | 4/25/2024 | ISMAEL HERNANDEZ |
| Tenant Habitability Plan | Cleared | 4/25/2024 | ISMAEL HERNANDEZ |
| Green Code | Cleared | 5/30/2024 | Hernan Arreola |
| Fire Marshal Fire Life Safety | Cleared | 6/12/2024 | SARAH ZHANG |
| DAS Clearance | Cleared | 6/27/2024 | Hernan Arreola |
Contact Information
| Architect | Chang,, Jerome C; Lic. No.: NA30767 | , |
| Contractor | M C S Builders Inc; Lic. No.: 876796-B | , |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 12/16/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| METHANE-Rough | 12/16/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 12/16/2024 | Partial Inspection | TIMOTHY POWELL |
| Green Building Rough | 1/24/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| METHANE-Rough | 1/24/2025 | Approved | TIMOTHY POWELL |
| Wood Frame | 1/24/2025 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 2/10/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 2/10/2025 | Partial Inspection | TIMOTHY POWELL |
| Footing/Foundation/Slab | 2/18/2025 | Partial Approval | TIMOTHY POWELL |
| Final | 8/27/2025 | Permit Finaled | LUIS CCAMACHO |
| Green Building Final | 8/27/2025 | Approved | LUIS CCAMACHO |
| Green Building Rough | 8/27/2025 | Approved | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 8/27/2025 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 8/27/2025 | Approved | LUIS CCAMACHO |
| Wood Frame | 8/27/2025 | Approved | LUIS CCAMACHO |