122 N WETHERLY DR 90048
Certificate Information: 122 N WETHERLY DR 90048
- Application / Permit
- 23016-10000-29040
- Plan Check / Job No.
- B23LA16079
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: By adding (1) SSCC at west elevation
- Permit Issued
- Issued on 3/27/2024
- Issuing Office
- Current Status
- Issued on 3/27/2024
Permit Application Status History
| Submitted | 8/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/7/2023 | JESSE VIDUYA |
| Corrections Issued | 9/11/2023 | JESSE VIDUYA |
| Quality Review Completed | 9/19/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 11/14/2023 | JESSE VIDUYA |
| Plan Check Approved | 11/22/2023 | JESSE VIDUYA |
| Issued | 3/27/2024 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 3/22/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Shaolian Sol K And Assoc Inc; Lic. No.: 720390-B | , |
| Contractor | Sks Construction; Lic. No.: 720390-B | , |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 15134 FRIAR ST VAN NUYS, CA 91411 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/24/2024 | Approved | JACOB MYERS |
| Deputy Drilled-In Anchors | 4/25/2024 | Partial Approval | JACOB MYERS |
| Deputy Steel/Welding | 4/25/2024 | Partial Approval | JACOB MYERS |
| Footing/Foundation/Slab | 4/25/2024 | Approved | JACOB MYERS |
| Deputy Reinf. Concrete | 4/26/2024 | Partial Approval | JACOB MYERS |
| Interior/Exterior Lathing | 5/1/2024 | Approved | JACOB MYERS |
| Final | 5/9/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 5/9/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/9/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 5/9/2024 | Conditional Approval | DARRYL ARNOLD |