2230 W FARGO ST 90039
Certificate Information: 2230 W FARGO ST 90039
- Application / Permit
- 23016-10000-29012
- Plan Check / Job No.
- B23LA16069
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- FULL REMODEL OF (E) FRONT UNIT
- Permit Issued
- Issued on 10/19/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 7/15/2024
Permit Application Status History
| Submitted | 8/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 9/6/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 9/12/2023 | APPLICANT |
| Applicant returned to address corrections | 10/17/2023 | CRISTINA SALAZAR |
| Plan Check Approved | 10/19/2023 | MINA HABILI |
| Issued | 10/19/2023 | APPLICANT |
| Permit Finaled | 7/12/2024 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/18/2023 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Velasco,, Jose Luis; Lic. No.: C76091 | 7901 4TH ST. N STE 5086 ST. PETERSBURG, FL 33702 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/8/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/20/2023 | Partial Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 12/29/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 12/29/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| PLUMBING-Rough | 12/29/2023 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/4/2024 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 1/9/2024 | Partial Inspection | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 1/23/2024 | Approved | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Approved | THOMAS LOGRASSO |
| HVAC-Rough | 1/23/2024 | Approved | THOMAS LOGRASSO |
| Insulation | 1/23/2024 | Approved | THOMAS LOGRASSO |
| MERV13>=Rough | 1/23/2024 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 2/21/2024 | Approved | THOMAS LOGRASSO |
| Shower Pan | 2/21/2024 | Approved | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 4/18/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Underground Mechanical | 4/18/2024 | Partial Approval | BRENDAN MORELLI |
| Final | 6/20/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| MERV13>=Final | 6/20/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 6/20/2024 | Approved | HAMIK HARTOUNIAN |
| Final | 7/5/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Final | 7/12/2024 | Permit Finaled | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/12/2024 | SGSOV Approved | HAMIK HARTOUNIAN |