1075 E AMOROSO PL 90291

Certificate Information: 1075 E AMOROSO PL 90291

Application / Permit
23016-10000-28893
Plan Check / Job No.
B23LA16034
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan Conversion of existing detached garage (420sf) into an ADU per state law
Permit Issued
Issued on 5/3/2024
Issuing Office
Current Status
CofO Issued on 6/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2023 APPLICANT
Assigned to Plan Check Engineer 8/30/2023 DANIEL SMILEY
Corrections Issued 8/31/2023 DANIEL SMILEY
Applicant returned to address corrections 4/2/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 4/16/2024 ZAW HAN
Plan Check Approved 4/17/2024 ZAW HAN
Issued 5/3/2024 APPLICANT
Permit Finaled 6/3/2026 CLAUDIO MORENO
CofO Issued 6/3/2026 CLAUDIO MORENO
Permit Finaled 6/3/2026 CLAUDIO MORENO

Permit Application Clearance Information

Address approval Cleared 10/31/2023 DARIN LAM
Sewer availability Cleared 10/31/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 11/1/2023 DARIN LAM
Specific Plan Cleared 2/28/2024 FREDDY GARCIA

Contact Information

Contractor J P Builders & Development Inc; Lic. No.: 992192-B       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 1543      HAWTHORNE, CA 90251

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/30/2024 Not Ready for Inspection RYAN BARNES
HVAC-Rough 5/30/2024 Not Ready for Inspection RYAN BARNES
PLUMBING-Rough 5/30/2024 Not Ready for Inspection RYAN BARNES
Deputy Drilled-In Anchors 7/16/2024 Conditional Approval JOHN MATTILLO
Footing/Foundation/Slab 7/17/2024 Approved JOHN MATTILLO
BUILDING-Rough-Frame 7/25/2024 Not Ready for Inspection RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Approved RYAN BARNES
Green Building Rough 7/25/2024 Approved RYAN BARNES
Wood Frame 7/25/2024 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Rough 7/29/2024 Partial Approval RYAN BARNES
HVAC-Rough 7/29/2024 Not Ready for Inspection RYAN BARNES
Interior/Exterior Lathing 7/29/2024 Partial Approval RYAN BARNES
PLUMBING-Rough 7/29/2024 Not Ready for Inspection RYAN BARNES
Drywall Nailing 8/12/2024 Partial Approval RYAN BARNES
ELECTRICAL-Rough 8/12/2024 Approved RYAN BARNES
HVAC-Rough 8/12/2024 Approved RYAN BARNES
PLUMBING-Rough 8/12/2024 Approved RYAN BARNES
Drywall Nailing 8/15/2024 Approved RYAN BARNES
ELECTRICAL-Rough 8/15/2024 Approved RYAN BARNES
Interior/Exterior Lathing 8/15/2024 Approved RYAN BARNES
BUILDING-Rough-Frame 9/5/2024 Approved RYAN BARNES
ELECTRICAL-Final 9/5/2024 Corrections Issued RYAN BARNES
Final 9/5/2024 Not Ready for Inspection RYAN BARNES
Green Building Final 9/5/2024 Approved RYAN BARNES
HVAC-Final 9/5/2024 Approved RYAN BARNES
PLUMBING-Final 9/5/2024 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 9/5/2024 SGSOV Approved RYAN BARNES
Smoke Detectors 9/5/2024 Approved RYAN BARNES
ELECTRICAL-Final 9/9/2024 Approved RYAN BARNES
Final 9/9/2024 Conditional Approval RYAN BARNES
HVAC-Final 9/9/2024 Approved RYAN BARNES
PLUMBING-Final 9/9/2024 Approved RYAN BARNES