1000 E WASHINGTON BLVD 101 90021
Certificate Information: 1000 E WASHINGTON BLVD 101 90021
- Application / Permit
- 23016-10000-28858
- Plan Check / Job No.
- B23LA16013
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TI to (E) Retail Space and combine adjacent tenant space.
- Permit Issued
- Issued on 2/8/2024
- Issuing Office
- Metro
- Current Status
- Issued on 2/8/2024
Permit Application Status History
| Submitted | 8/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2023 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 9/12/2023 | APPLICANT |
| Corrections Issued | 9/29/2023 | HERNAN ARREOLA |
| Quality Review Completed | 9/29/2023 | PETER KIM |
| Building Plans Picked Up | 10/11/2023 | APPLICANT |
| Applicant returned to address corrections | 1/18/2024 | HERNAN ARREOLA |
| Plan Check Approved | 2/8/2024 | HERNAN ARREOLA |
| Issued | 2/8/2024 | APPLICANT |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 11/13/2023 | ELIZABETH GALLARDO |
| "D" conditions | Cleared | 12/26/2023 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 12/26/2023 | HELEN JADALI |
| Green Code | Cleared | 1/10/2024 | HERNAN ARREOLA |
| DAS Clearance | Cleared | 1/12/2024 | SHINE LIN |
Contact Information
| Contractor | Pacific General Contractor Builders Inc; Lic. No.: 1031596-B | 3811 WACKER DRIVE JURUPA VALLEY, CA 91752 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2024 | Partial Approval | JEROME BLACKWOOD |
| Light Gage Steel Frame | 3/27/2024 | Partial Inspection | RONALD JIMENEZ |
| Light Gage Steel Frame | 3/28/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Insulation | 4/5/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 4/10/2024 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 4/11/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/11/2024 | Partial Inspection | LUIS CCAMACHO |
| Insulation | 4/24/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 4/24/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 4/30/2024 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 4/30/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| T-Bar Ceiling | 5/8/2024 | Partial Approval | LUIS CCAMACHO |
| T-Bar Ceiling | 6/5/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 7/3/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 7/10/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 7/18/2024 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 7/19/2024 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 8/14/2024 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/16/2024 | Partial Approval | LUIS CCAMACHO |
| Final | 9/17/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 9/17/2024 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 9/17/2024 | Approved | JEROME BLACKWOOD |