1000 E WASHINGTON BLVD 101 90021

Certificate Information: 1000 E WASHINGTON BLVD 101 90021

Application / Permit
23016-10000-28858
Plan Check / Job No.
B23LA16013
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
TI to (E) Retail Space and combine adjacent tenant space.
Permit Issued
Issued on 2/8/2024
Issuing Office
Metro
Current Status
Issued on 2/8/2024

Permit Application Status History

Submitted 8/25/2023 APPLICANT
Assigned to Plan Check Engineer 8/31/2023 HERNAN ARREOLA
Disabled Access Plans Picked Up 9/12/2023 APPLICANT
Corrections Issued 9/29/2023 HERNAN ARREOLA
Quality Review Completed 9/29/2023 PETER KIM
Building Plans Picked Up 10/11/2023 APPLICANT
Applicant returned to address corrections 1/18/2024 HERNAN ARREOLA
Plan Check Approved 2/8/2024 HERNAN ARREOLA
Issued 2/8/2024 APPLICANT

Permit Application Clearance Information

Redevelopment Project Area Cleared 11/13/2023 ELIZABETH GALLARDO
"D" conditions Cleared 12/26/2023 HELEN JADALI
Community Plan Implem. Overlay Cleared 12/26/2023 HELEN JADALI
Green Code Cleared 1/10/2024 HERNAN ARREOLA
DAS Clearance Cleared 1/12/2024 SHINE LIN

Contact Information

Contractor Pacific General Contractor Builders Inc; Lic. No.: 1031596-B 3811 WACKER DRIVE      JURUPA VALLEY, CA 91752

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 3/14/2024 Partial Approval JEROME BLACKWOOD
Light Gage Steel Frame 3/27/2024 Partial Inspection RONALD JIMENEZ
Light Gage Steel Frame 3/28/2024 Not Ready for Inspection LUIS CCAMACHO
Insulation 4/5/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 4/10/2024 Partial Approval JEROME BLACKWOOD
Insulation 4/11/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/11/2024 Partial Inspection LUIS CCAMACHO
Insulation 4/24/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 4/24/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 4/30/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 4/30/2024 Not Ready for Inspection LUIS CCAMACHO
T-Bar Ceiling 5/8/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 6/5/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 7/3/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/10/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 7/18/2024 Partial Approval LUIS CCAMACHO
Drywall Nailing 7/19/2024 Partial Approval LUIS CCAMACHO
Light Gage Steel Frame 8/14/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 8/16/2024 Partial Approval LUIS CCAMACHO
Final 9/17/2024 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 9/17/2024 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 9/17/2024 Approved JEROME BLACKWOOD