2953-2955 S BRONSON AVE 90018

Certificate Information: 2953-2955 S BRONSON AVE 90018

Application / Permit
23016-10000-28635
Plan Check / Job No.
B23LA15895
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
INTERIOR REMODEL TO (E) DUPLEX TO CONVERT FROM 2 BED AND 1 BATH TO 3BED 2BATH. AND RELOCATE KITCHEN.
Permit Issued
Issued on 10/19/2023
Issuing Office
Current Status
Permit Finaled on 8/6/2024

Permit Application Status History

Submitted 8/24/2023 APPLICANT
Assigned to Plan Check Engineer 8/28/2023 NEHEMIAS RAMOS
Corrections Issued 8/30/2023 NEHEMIAS RAMOS
Applicant returned to address corrections 10/5/2023 NEHEMIAS RAMOS
Plan Check Approved 10/18/2023 NEHEMIAS RAMOS
Issued 10/19/2023 APPLICANT
CofO in Progress 8/2/2024 JUSTIN HAWLEY
Permit Finaled 8/6/2024 JOAQUIN GREENOUGH
No Progress 8/6/2024 JOAQUIN GREENOUGH
CofO in Progress 8/6/2024 JOAQUIN GREENOUGH

Permit Application Clearance Information

Tenant Habitability Plan Cleared 9/27/2023 RICARDO BOHORQUEZ
Sewer availability Cleared 10/11/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/13/2023 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 10/20/2023 Not Ready for Inspection CALEB MEISTER
Pre-Inspection 10/20/2023 Not Ready for Inspection CALEB MEISTER
BUILDING-Rough-Frame 11/29/2023 Not Ready for Inspection RONNIE MINDANAO
HVAC-Rough 11/29/2023 Not Ready for Inspection RONNIE MINDANAO
PLUMBING-Rough 11/29/2023 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 Partial Approval JUSTIN HAWLEY
HVAC-Rough 12/12/2023 Not Ready for Inspection JUSTIN HAWLEY
PLUMBING-Rough 12/12/2023 Corrections Issued JUSTIN HAWLEY
ELECTRICAL-Rough 12/21/2023 Approved JUSTIN HAWLEY
HVAC-Rough 12/21/2023 Corrections Issued JUSTIN HAWLEY
PLUMBING-Rough 12/21/2023 Approved JUSTIN HAWLEY
Wood Frame 12/21/2023 Not Ready for Inspection JUSTIN HAWLEY
BUILDING-Rough-Frame 1/4/2024 Corrections Issued JUSTIN HAWLEY
HVAC-Rough 1/4/2024 Corrections Issued JUSTIN HAWLEY
Interior/Exterior Lathing 1/4/2024 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 1/8/2024 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 1/8/2024 Partial Approval BRENDAN MORELLI
Insulation 1/11/2024 Approved BRENDAN MORELLI
Drywall Nailing 1/30/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 1/30/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 6/18/2024 Not Ready for Inspection JUSTIN HAWLEY
Final 6/18/2024 Corrections Issued JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 6/18/2024 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 7/24/2024 Approved JUSTIN HAWLEY
Final 7/24/2024 Corrections Issued JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 7/24/2024 SGSOV Approved JUSTIN HAWLEY
Final 8/2/2024 OK to Issue CofO JUSTIN HAWLEY
Final 8/6/2024 Permit Finaled JOAQUIN GREENOUGH