2303 S FIGUEROA WAY 90007
Certificate Information: 2303 S FIGUEROA WAY 90007
- Application / Permit
- 23016-10000-28466
- Plan Check / Job No.
- B23LA15795
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) School Building
- Work Description
- Seismic Retrofit to an existing 3-story charter school per NDC Ordinance 183893 (NDC-863)
- Permit Issued
- Issued on 7/24/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 7/24/2025
Permit Application Status History
| Submitted | 8/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2023 | GARO TELMI |
| Plans on Hold | 9/18/2023 | LIPING TENG |
| Disabled Access Plans Picked Up | 4/2/2024 | APPLICANT |
| Building Plans Picked Up | 3/12/2025 | APPLICANT |
| Hold Released | 7/22/2025 | DANIEL CHAN |
| Corrections Issued | 7/22/2025 | GARO TELMI |
| Quality Review Completed | 7/23/2025 | DANIEL CHAN |
| Plan Check Approved | 7/23/2025 | GARO TELMI |
| Issued | 7/24/2025 | APPLICANT |
| Permit Finaled-Status Void | 2/26/2026 | ALFREDO LOPEZ |
| Permit Finaled-Status Void | 2/26/2026 | ALFREDO LOPEZ |
| Re-Activate Permit | 5/19/2026 | ALFREDO LOPEZ |
| Re-Activate Permit | 5/20/2026 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2025 | JEREMY CHOK |
| "Q" conditions | Cleared | 4/11/2025 | FIPE LEILUA |
| ZA Case | Cleared | 4/11/2025 | FIPE LEILUA |
| City Hist. Cultural Monument | Cleared | 4/15/2025 | RAFAEL FONTES |
| Historic monument | Cleared | 4/15/2025 | RAFAEL FONTES |
| Miscellaneous | Cleared | 4/15/2025 | RAFAEL FONTES |
| Metro Rail approval | Cleared | 4/17/2025 | JENNIFER SU |
| DAS Clearance | Cleared | 7/17/2025 | EDDIE GARIN |
| Work Adjacent to Public Way | Cleared | 7/21/2025 | ERIK BEASLEY |
| Green Code | Cleared | 7/23/2025 | GARO TELMI |
Contact Information
| Architect | Tomalevski,, Vladimir Bogdanov; Lic. No.: C22417 | 8416 HAROLD WAY L&V TOMALEVSKI ARCHITECTS, INC. LOS ANGELES, CA 90069 |
| Contractor | Smartx Builders Inc; Lic. No.: 1053542-B | 13455 VENTURA BLVD #237 SHERMAN OAKS, CA 91423 |
| Engineer | Ha,, Seungil; Lic. No.: S4164 | 3454 W 1ST ST LOS ANGELES, CA 90004 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/28/2025 | Conditional Approval | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 7/28/2025 | Partial Approval | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 7/28/2025 | Partial Approval | ALFREDO LOPEZ |
| Deputy Drilled-In Anchors | 8/5/2025 | Conditional Approval | ALFREDO LOPEZ |
| Reinforced Concrete Frame | 8/5/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Deputy Shotcrete | 8/6/2025 | Conditional Approval | ALFREDO LOPEZ |
| Reinforced Concrete Frame | 8/6/2025 | Partial Inspection | ALFREDO LOPEZ |
| Deputy Shotcrete | 8/7/2025 | Conditional Approval | DARRYL ARNOLD |
| Deputy Shotcrete | 8/8/2025 | Conditional Approval | DARRYL ARNOLD |
| Deputy Shotcrete | 8/11/2025 | Conditional Approval | DARRYL ARNOLD |
| Deputy Shotcrete | 8/12/2025 | Conditional Approval | DARRYL ARNOLD |
| Deputy Shotcrete | 8/13/2025 | Conditional Approval | DARRYL ARNOLD |
| Deputy Shotcrete | 8/14/2025 | Partial Approval | ALFREDO LOPEZ |
| Reinforced Concrete Frame | 8/14/2025 | Partial Approval | ALFREDO LOPEZ |
| Reinforced Concrete Frame | 8/20/2025 | Partial Approval | ALFREDO LOPEZ |
| Reinforced Concrete Frame | 10/23/2025 | Partial Approval | ALFREDO LOPEZ |
| Final | 1/12/2026 | No Access for Inspection | RAFAEL CORTES |
| Green Building Final | 1/12/2026 | No Access for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 1/12/2026 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 1/12/2026 | No Access for Inspection | RAFAEL CORTES |
| Final | 1/21/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 1/21/2026 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 1/21/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 2/12/2026 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/12/2026 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 2/12/2026 | Partial Inspection | ALFREDO LOPEZ |
| Final | 2/26/2026 | Partial Approval | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/26/2026 | SGSOV Not Required | ALFREDO LOPEZ |
| Smoke Detectors | 2/26/2026 | Approved | ALFREDO LOPEZ |