5706-5708 S VAN NESS AVE 90062

Certificate Information: 5706-5708 S VAN NESS AVE 90062

Application / Permit
23016-10000-28377
Plan Check / Job No.
B23LA15766
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Convert existing attached garage to Accessory Dwelling Unit (494 sf) per state law CA G.C. 65852.2(e)(1)(C) . Work per wood frame prescriptive provisions . Parking reduction per AB 2097 .
Permit Issued
Issued on 1/19/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2023 APPLICANT
Assigned to Plan Check Engineer 8/23/2023 GEORGE ALVAREZ
Corrections Issued 8/23/2023 GEORGE ALVAREZ
Applicant returned to address corrections 1/12/2024 NEHEMIAS RAMOS
Issued 1/19/2024 APPLICANT
CofO in Progress 5/5/2025 BARRY HACHE
Permit Finaled 5/6/2025 DEROLD HAUFF
CofO Issued 5/6/2025 DEROLD HAUFF
Permit Finaled 5/6/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/9/2024 ERIK BEASLEY
Sewer availability Cleared 1/9/2024 ERIK BEASLEY
Tenant Habitability Plan Cleared 1/11/2024 RICARDO BOHORQUEZ
Eng Process Fee Ord 176,300 Cleared 1/16/2024 KHAING AYE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/2/2024 Partial Approval BRENDAN MORELLI
Sewer 4/2/2024 Approved BRENDAN MORELLI
ELECTRICAL-Rough 4/22/2024 Partial Inspection CRAIG DAVIS
Footing/Foundation/Slab 4/22/2024 Approved CRAIG DAVIS
BUILDING-Rough-Frame 6/25/2024 Corrections Issued CRAIG DAVIS
ELECTRICAL-Rough 6/25/2024 Corrections Issued CRAIG DAVIS
Gas Test 6/25/2024 Approved CRAIG DAVIS
Green Building Rough 6/25/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 6/25/2024 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 7/11/2024 Approved CRAIG DAVIS
Gas Test 7/11/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 7/11/2024 Partial Approval CRAIG DAVIS
Wood Frame 7/11/2024 Partial Approval CRAIG DAVIS
HVAC-Rough 7/18/2024 Approved SABAS ALONSO
Insulation 7/18/2024 Conditional Approval SABAS ALONSO
Interior/Exterior Lathing 7/18/2024 Partial Approval SABAS ALONSO
PLUMBING-Rough 7/18/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Approved SABAS ALONSO
Green Building Rough 7/22/2024 Approved SABAS ALONSO
Insulation 7/22/2024 Approved SABAS ALONSO
Drywall Nailing 8/2/2024 Approved ALEX COLIN
Interior/Exterior Lathing 8/2/2024 Approved ALEX COLIN
Final 3/18/2025 Corrections Issued BARRY HACHE
Green Building Final 3/18/2025 Approved BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/18/2025 SGSOV Not Ready BARRY HACHE
Smoke Detectors 3/18/2025 Corrections Issued BARRY HACHE
BUILDING-Rough-Frame 3/27/2025 Approved BARRY HACHE
Final 3/27/2025 Not Ready for Inspection BARRY HACHE
SGSOV-Seismic Gas S/O Valve 3/27/2025 SGSOV Approved BARRY HACHE
Smoke Detectors 3/27/2025 Approved BARRY HACHE
ELECTRICAL-Final 4/1/2025 Approved BARRY HACHE
Final 4/4/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 4/8/2025 Approved BARRY HACHE
PLUMBING-Final 4/8/2025 Approved BARRY HACHE
Final 4/14/2025 Conditional Approval BARRY HACHE
ELECTRICAL-Final 4/28/2025 Approved BARRY HACHE
Service/Power Release 4/28/2025 Approved BARRY HACHE
Final 5/2/2025 OK to Issue CofO BARRY HACHE
Service/Power Release 5/2/2025 Approved BARRY HACHE