1605 N BENTON WAY 90026

Certificate Information: 1605 N BENTON WAY 90026

Application / Permit
23016-10000-28069
Plan Check / Job No.
B23LA15605
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Conversion of existing detached garage to ADU (256SQFT) per CA Govt. Code 65852.2(e)(1)(A) ***COMPLY WITH DEPARTMENT ORDER effective date 12/31/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE***
Permit Issued
Issued on 12/1/2023
Issuing Office
Current Status
CofO Issued on 5/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2023 APPLICANT
Assigned to Plan Check Engineer 8/25/2023 DANIEL SMILEY
Corrections Issued 8/28/2023 DANIEL SMILEY
Applicant returned to address corrections 9/2/2023 KHUONG TRUONG
Plan Check Approved 11/30/2023 KHUONG TRUONG
Issued 12/1/2023 APPLICANT
CofO in Progress 4/24/2024 COREY HUPP
Permit Finaled 5/1/2024 DANIEL SANCHEZ
CofO Issued 5/1/2024 DANIEL SANCHEZ
Permit Finaled 5/1/2024 DANIEL SANCHEZ

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/1/2023 RUSSELL BONVOULOIR
Address approval Cleared 9/6/2023 JESSICA OPINION
Sewer availability Cleared 9/6/2023 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 9/11/2023 JESSICA OPINION
Miscellaneous Cleared 9/25/2023 ALBERT TAM
Construction near power lines Cleared 11/29/2023 RIDWAN HARDY
Construction within easement Cleared 11/29/2023 RIDWAN HARDY

Contact Information

Architect Sabikhi,, Sidhartha; Lic. No.: C32564 933 MICHELTORENA ST      LOS ANGELES, CA 90026
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 1/12/2024 Not Ready for Inspection COREY HUPP
Green Building Rough 1/12/2024 Approved COREY HUPP
Insulation 1/12/2024 Not Ready for Inspection COREY HUPP
Interior/Exterior Lathing 1/12/2024 Not Ready for Inspection COREY HUPP
Rough-Elec/Plmb/HVAC 1/12/2024 Not Ready for Inspection COREY HUPP
Underground Mechanical 1/19/2024 Approved COREY HUPP
BUILDING-Rough-Frame 1/24/2024 Corrections Issued COREY HUPP
ELECTRICAL-Rough 1/26/2024 Not Ready for Inspection COREY HUPP
Underground Mechanical 2/8/2024 Approved COREY HUPP
Footing/Foundation/Slab 2/14/2024 Conditional Approval COREY HUPP
BUILDING-Rough-Frame 2/21/2024 Corrections Issued COREY HUPP
Rough-Elec/Plmb/HVAC 2/21/2024 Approved COREY HUPP
BUILDING-Rough-Frame 2/26/2024 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 3/5/2024 Approved COREY HUPP
Insulation 3/7/2024 Approved COREY HUPP
Interior/Exterior Lathing 3/7/2024 Approved COREY HUPP
Drywall Nailing 3/11/2024 Approved COREY HUPP
Final 3/28/2024 Corrections Issued COREY HUPP
Green Building Final 3/28/2024 Approved COREY HUPP
SGSOV-Seismic Gas S/O Valve 3/28/2024 SGSOV Not Ready COREY HUPP
Smoke Detectors 3/28/2024 Approved COREY HUPP
Final 4/2/2024 OK to Issue CofO COREY HUPP
SGSOV-Seismic Gas S/O Valve 4/2/2024 SGSOV Approved COREY HUPP