1235 N SUNSET PLAZA DR 90069
Certificate Information: 1235 N SUNSET PLAZA DR 90069
- Application / Permit
- 23016-10000-27720
- Plan Check / Job No.
- B23LA15336
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: INTERIOR REMODEL THROUGHOUT(E) SINGLE FAMILY RESIDENCE. ALL WORK PER ENG.
- Permit Issued
- Issued on 5/30/2024
- Issuing Office
- Current Status
- Issued on 5/30/2024
Permit Application Status History
| Submitted | 8/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/22/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 9/16/2023 | LUISANGEL VALENZUELA |
| Issued | 5/30/2024 | APPLICANT |
Permit Application Clearance Information
| Hold | Cleared | 8/7/2024 | TERESA RIVAS |
Contact Information
| Contractor | Allen Design + Build Inc; Lic. No.: 1073018-B | , |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2024 | Corrections Issued | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 6/4/2024 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/5/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/7/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 8/9/2024 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 8/9/2024 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Rough | 8/9/2024 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/16/2024 | No Access for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | No Access for Inspection | RAUL BARAJAS |
| Insulation | 8/16/2024 | No Access for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/29/2024 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Approved | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 8/29/2024 | Approved | RAUL BARAJAS |
| Insulation | 9/4/2024 | Approved | RAUL BARAJAS |
| Drywall Nailing | 9/12/2024 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/12/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/13/2024 | Approved | RAUL BARAJAS |
| Final | 3/2/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Not Ready | DAVID WILLIAMS |
| Smoke Detectors | 3/2/2026 | Approved | DAVID WILLIAMS |