5631 W LA MIRADA AVE 90038
Certificate Information: 5631 W LA MIRADA AVE 90038
- Application / Permit
- 23016-10000-27668
- Plan Check / Job No.
- B23LA15304
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2-STORY ACCESSORY LIVING QUARTERS (1838 SF) INTO A NEW DETACHED ADU
- Permit Issued
- Issued on 10/16/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2023 | JOSEPH RAFOLS |
| Corrections Issued | 8/24/2023 | JOSEPH RAFOLS |
| Building Plans Picked Up | 8/30/2023 | APPLICANT |
| Plan Check Approved | 10/4/2023 | ADAM HEGAZI |
| Issued | 10/16/2023 | APPLICANT |
| CofO in Progress | 4/1/2024 | BRIAN SULLIVAN |
| Permit Finaled | 8/6/2024 | RONALD MYRICK |
| CofO Issued | 8/6/2024 | RONALD MYRICK |
| Permit Finaled | 8/6/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2023 | ERIK BEASLEY |
| Sewer availability | Cleared | 9/11/2023 | ERIK BEASLEY |
| Historic Resource Verification | Cleared | 9/21/2023 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 9/22/2023 | DAVID URITA |
| Address approval | Cleared | 9/29/2023 | AMBER CAMPBELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/13/2023 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 11/13/2023 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 11/13/2023 | Approved | BRIAN SULLIVAN |
| Shower Pan | 11/13/2023 | Approved | BRIAN SULLIVAN |
| Wood Frame | 11/13/2023 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 11/20/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 11/20/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Gas Test | 11/20/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Insulation | 11/20/2023 | Corrections Issued | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 11/20/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| MERV13>=Rough | 11/20/2023 | Approved | BRIAN SULLIVAN |
| Wood Frame | 11/20/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/6/2023 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/6/2023 | Approved | STUART CHAPMAN |
| Insulation | 12/6/2023 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/6/2023 | Approved | STUART CHAPMAN |
| Wood Frame | 12/6/2023 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/14/2023 | Approved | BRIAN SULLIVAN |
| Insulation | 12/14/2023 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 12/22/2023 | Approved | BRIAN SULLIVAN |
| Final | 3/22/2024 | Corrections Issued | ROY SPAULDING |
| MERV13>=Final | 3/22/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 3/22/2024 | Approved | ROY SPAULDING |
| Final | 3/29/2024 | OK to Issue CofO | BRIAN SULLIVAN |