2812 W TEMPLE ST 90026
Certificate Information: 2812 W TEMPLE ST 90026
- Application / Permit
- 23016-10000-27575
- Plan Check / Job No.
- B23LA15276
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- PROJECT HOMEKEY: MULTIFAMILY HOUSING PROGRAM PER GCS 50675.1.3. ALTERATIONS TO (E) MIXED-USE APARTMENT (18010-20000-05663). ALTERATIONS INCLUDE ACCESSIBILITY UPGRADES. 11% of total units for Mobility units and 4% of total units for Hearing or Vision Impaired units.
- Permit Issued
- Issued on 1/11/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/1/2026
Permit Application Status History
| Submitted | 8/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2023 | MANUEL MONTUFAR |
| Corrections Issued | 9/19/2023 | MANUEL MONTUFAR |
| Quality Review Completed | 9/20/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/12/2023 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 10/31/2023 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 11/16/2023 | MANUEL MONTUFAR |
| Plan Check Approved | 12/22/2023 | MANUEL MONTUFAR |
| Issued | 1/11/2024 | APPLICANT |
| Permit Finaled | 6/1/2026 | RAFAEL CORTES |
Permit Application Clearance Information
| Density Bonus | Cleared | 10/5/2023 | MARITES CUNANAN |
| Fire Marshal Fire Life Safety | Cleared | 11/10/2023 | MENOA AGHAJANI |
| Miscellaneous | Cleared | 11/15/2023 | DANIEL CORONADO |
| Green Code | Cleared | 11/16/2023 | Rodolfo Arias |
| DAS Clearance | Cleared | 11/21/2023 | Rodolfo Arias |
| Public Housing | Cleared | 12/11/2023 | JOEL LAUNCHBAUGH |
Contact Information
| Architect | Han,, Sangyoul; Lic. No.: C32263 | 7433 SHADYGLADE AVENUE #3 NORTH HOLLYWOOD, CA 91605 |
| Contractor | Walton Construction Inc; Lic. No.: 1034491-B | , |
| Engineer | Yoon,, Philip; Lic. No.: C94664 | 1221 W 3RD ST APT 234 LOS ANGELES, CA 90017 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/27/2024 | Approved | RAFAEL ESPINOZA |
| Wood Frame | 5/6/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 6/17/2024 | Approved | RAFAEL ESPINOZA |
| Drywall Nailing | 6/27/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 7/25/2024 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 7/31/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 9/5/2024 | Partial Approval | NICK DANERI |
| Drywall Nailing | 9/12/2024 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 10/23/2024 | Partial Approval | RAFAEL CORTES |
| Drywall Nailing | 10/31/2024 | Partial Approval | RAFAEL CORTES |
| Pre-Inspection | 11/4/2024 | Approved | RAFAEL CORTES |
| Light Gage Steel Frame | 11/20/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Insulation | 12/9/2024 | Partial Approval | RAFAEL CORTES |
| Final | 1/28/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Final | 1/28/2025 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 1/28/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Deputy Drilled-In Anchors | 2/3/2025 | Conditional Approval | RAFAEL CORTES |
| Final | 2/10/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Green Building Final | 2/10/2025 | Approved | RAFAEL ESPINOZA |
| Smoke Detectors | 2/10/2025 | Approved | RAFAEL ESPINOZA |
| Final | 3/2/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 4/3/2026 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 6/1/2026 | Permit Finaled | RAFAEL CORTES |