8014-8016 S DENROCK AVE 90045

Certificate Information: 8014-8016 S DENROCK AVE 90045

Application / Permit
23016-10000-27156
Plan Check / Job No.
B23LA15095
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT A PORTION OF (E) SFD TO JADU (491 SQFT) PER STATE LAW
Permit Issued
Issued on 12/13/2023
Issuing Office
Metro
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2023 APPLICANT
Assigned to Plan Check Engineer 8/21/2023 KHUONG TRUONG
Corrections Issued 8/22/2023 KHUONG TRUONG
Applicant returned to address corrections 10/12/2023 JOSEPH RAFOLS
Applicant returned to address corrections 10/20/2023 NEHEMIAS RAMOS
Plan Check Approved 12/8/2023 MINA HABILI
Issued 12/13/2023 APPLICANT
CofO in Progress 8/2/2024 BOBBY KEY
Permit Finaled 8/6/2024 DANIEL ORRANTE
CofO Issued 8/6/2024 DANIEL ORRANTE
Permit Finaled 8/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/31/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 8/31/2023 ANTHONY MAINEZ
Sewer availability Cleared 8/31/2023 ANTHONY MAINEZ
Specific Plan Cleared 10/11/2023 PEDRO AYALA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/8/2024 Partial Inspection TEMISTOCLES CAAL
BUILDING-Rough-Frame 6/5/2024 Approved BOBBY KEY
ELECTRICAL-Final 6/5/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 6/5/2024 Approved BOBBY KEY
HVAC-Rough 6/5/2024 Corrections Issued BOBBY KEY
Insulation 6/5/2024 Approved BOBBY KEY
Interior/Exterior Lathing 6/5/2024 Approved BOBBY KEY
PLUMBING-Rough 6/5/2024 Conditional Approval BOBBY KEY
Drywall Nailing 6/14/2024 Approved RICHARD STEINBACH
PLUMBING-Rough 6/14/2024 Approved RICHARD STEINBACH
ELECTRICAL-Final 7/30/2024 Approved RICHARD STEINBACH
Final 7/30/2024 Corrections Issued RICHARD STEINBACH
HVAC-Final 7/30/2024 Approved RICHARD STEINBACH
PLUMBING-Final 7/30/2024 Approved RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 7/30/2024 SGSOV Approved RICHARD STEINBACH
Smoke Detectors 7/30/2024 Approved RICHARD STEINBACH
Final 8/2/2024 OK to Issue CofO BOBBY KEY
Service/Power Release 8/2/2024 Approved BOBBY KEY