3140 N STOCKBRIDGE AVE 90032
Certificate Information: 3140 N STOCKBRIDGE AVE 90032
- Application / Permit
- 23016-10000-27062
- Plan Check / Job No.
- B23LA15056
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERSION OF EXISTING DETACHED 2-CAR GARAGE WITH NEW ADDITION INTOA DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 1/24/2024
- Issuing Office
- Current Status
- CofO Issued on 10/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/17/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 10/4/2023 | KEVIN MORALES |
| Plan Check Approved | 12/13/2023 | KEVIN MORALES |
| Issued | 1/24/2024 | APPLICANT |
| CofO in Progress | 9/26/2024 | BRENDAN MORELLI |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
| CofO Issued | 10/1/2024 | RUBEN SALAS |
| Permit Finaled | 10/1/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/28/2023 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 8/28/2023 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2023 | AMBER CAMPBELL |
| Sewer availability | Cleared | 8/31/2023 | AMBER CAMPBELL |
| Grading Pre-Inspection | Cleared | 10/19/2023 | RUSSELL BONVOULOIR |
| Construction near power lines | Cleared | 12/10/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/30/2024 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 1/30/2024 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/15/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 3/26/2024 | Partial Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/1/2024 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 4/25/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 4/25/2024 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/3/2024 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 5/3/2024 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Approved | LILIANA PORTILLO |
| Gas Test | 5/3/2024 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 5/3/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 5/3/2024 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 5/14/2024 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 5/14/2024 | Partial Approval | BRENDAN MORELLI |
| Insulation | 5/30/2024 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 6/11/2024 | Approved | LILIANA PORTILLO |
| Insulation | 6/11/2024 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 6/28/2024 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | BRENDAN MORELLI |
| Final | 9/19/2024 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 9/19/2024 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 9/19/2024 | Approved | BRENDAN MORELLI |
| Final | 9/24/2024 | OK to Issue CofO | BRENDAN MORELLI |
| Service/Power Release | 9/24/2024 | Approved | BRENDAN MORELLI |