2029 N KEITH ST 90031

Certificate Information: 2029 N KEITH ST 90031

Application / Permit
23016-10000-26787
Plan Check / Job No.
B23LA14905
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
EXTERIOR/INTERIOR ALTERATION AND TENANT IMPORVEMENT OF AN EXISTING TWO STORY BUILDING . WORK TO INCLUDE EXTERIOR AND INTERIOR RAMPS . AND RECONFIGURE RESTROOM LAYOUTS . (NO CHANGE IN PARKING)
Permit Issued
Issued on 9/8/2023
Issuing Office
Metro
Current Status
Permit Finaled on 12/26/2023

Permit Application Status History

Submitted 8/10/2023 APPLICANT
Assigned to Plan Check Engineer 8/18/2023 AUNG SOE
Corrections Issued 8/23/2023 AUNG SOE
Building Plans Picked Up 8/24/2023 APPLICANT
Plan Check Approved 9/6/2023 GEORGE ALVAREZ
Issued 9/8/2023 APPLICANT
Permit Finaled 12/26/2023 RAMAZANALI ALMASI

Permit Application Clearance Information

ZA Case Cleared 9/8/2023 RYAN LY
ZA Case Cleared 9/8/2023 RYAN LY
ZA Case Cleared 9/8/2023 RYAN LY

Contact Information

Architect Lahmon,, Mark Karl; Lic. No.: C30068 3834 WILLAT AVENUE      CULVER CITY, CA 90278
Contractor Ponderosa Pines Gen Contractors; Lic. No.: 450947-B 9616 RIESHEL STREET      PICO RIVERA, CA 90660

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 10/17/2023 Not Ready for Inspection RAFAEL CORTES
Interior/Exterior Lathing 10/17/2023 Not Ready for Inspection RAFAEL CORTES
Drywall Nailing 10/24/2023 Not Ready for Inspection RAFAEL CORTES
Insulation 10/24/2023 Approved RAFAEL CORTES
Wood Frame 10/24/2023 Approved RAFAEL CORTES
Drywall Nailing 10/31/2023 Approved RAFAEL CORTES
Final 12/20/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 12/20/2023 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 12/20/2023 Not Ready for Inspection RAMAZANALI ALMASI
Special/Order Compliance 12/21/2023 No Access for Inspection RAFAEL CORTES
Final 12/22/2023 Partial Inspection RAMAZANALI ALMASI
Final 12/26/2023 Permit Finaled RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 12/26/2023 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 12/26/2023 Approved RAMAZANALI ALMASI