911 N LINDA FLORA DR 90049

Certificate Information: 911 N LINDA FLORA DR 90049

Application / Permit
23016-10000-26747
Plan Check / Job No.
B23LA14875
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: REMODEL TO REFRAME (E) ROOF OF THE SINGLE FAMILY DWELLING AND STRUCTURAL ALTERATIONS TO (E) SFD PER ENGINEER DESIGN. NO CHANGE IN SQUARE FOOTAGE OR MAX HEIGHT.
Permit Issued
Issued on 8/21/2023
Issuing Office
Current Status
Permit Finaled on 4/6/2026

Permit Application Status History

Submitted 8/10/2023 APPLICANT
Assigned to Plan Check Engineer 8/15/2023 OMAR GARNICA
Plan Check Approved 8/16/2023 OMAR GARNICA
Issued 8/21/2023 APPLICANT
Permit Finaled 4/1/2026 EVAN COOPER

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Mirzadeh,, Amir; Lic. No.: C58119 P O BOX 572110      TARZANA, CA 91357

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/20/2023 Approved CARLOS MATAMOROS
Special/Order Compliance 10/20/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 10/30/2023 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 11/1/2023 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 11/3/2023 Partial Approval CARLOS MATAMOROS
Gas Test 11/3/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 11/3/2023 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 2/28/2024 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 2/28/2024 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 2/28/2024 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 4/1/2024 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 4/1/2024 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 4/1/2024 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 4/9/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 4/26/2024 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 4/30/2024 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 4/30/2024 Approved CARLOS MATAMOROS
Green Building Rough 4/30/2024 Approved CARLOS MATAMOROS
HVAC-Rough 4/30/2024 Approved CARLOS MATAMOROS
Insulation 5/30/2024 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 5/30/2024 Corrections Issued TEMISTOCLES CAAL
Insulation 6/12/2024 Corrections Issued CARLOS MATAMOROS
Insulation 7/17/2024 Corrections Issued CARLOS MATAMOROS
Insulation 7/23/2024 Partial Approval CARLOS MATAMOROS
Insulation 7/25/2024 Approved CARLOS MATAMOROS
Drywall Nailing 8/22/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/22/2024 Approved CARLOS MATAMOROS
Shower Pan 9/25/2024 Approved CARLOS MATAMOROS
Gas Test 9/16/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 9/26/2025 Corrections Issued CARLOS MATAMOROS
HVAC-Final 9/26/2025 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 9/26/2025 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 4/1/2026 Approved EVAN COOPER
Final 4/1/2026 Permit Finaled EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Approved EVAN COOPER
Smoke Detectors 4/1/2026 Approved EVAN COOPER