911 N LINDA FLORA DR 90049
Certificate Information: 911 N LINDA FLORA DR 90049
- Application / Permit
- 23016-10000-26747
- Plan Check / Job No.
- B23LA14875
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan: REMODEL TO REFRAME (E) ROOF OF THE SINGLE FAMILY DWELLING AND STRUCTURAL ALTERATIONS TO (E) SFD PER ENGINEER DESIGN. NO CHANGE IN SQUARE FOOTAGE OR MAX HEIGHT.
- Permit Issued
- Issued on 8/21/2023
- Issuing Office
- Current Status
- Permit Finaled on 4/6/2026
Permit Application Status History
| Submitted | 8/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2023 | OMAR GARNICA |
| Plan Check Approved | 8/16/2023 | OMAR GARNICA |
| Issued | 8/21/2023 | APPLICANT |
| Permit Finaled | 4/1/2026 | EVAN COOPER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mirzadeh,, Amir; Lic. No.: C58119 | P O BOX 572110 TARZANA, CA 91357 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/20/2023 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 10/20/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/30/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/1/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 11/3/2023 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 11/3/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/3/2023 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/28/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/28/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/28/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/1/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 4/1/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 4/1/2024 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 4/9/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/26/2024 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/30/2024 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 4/30/2024 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 4/30/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 4/30/2024 | Approved | CARLOS MATAMOROS |
| Insulation | 5/30/2024 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 5/30/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Insulation | 6/12/2024 | Corrections Issued | CARLOS MATAMOROS |
| Insulation | 7/17/2024 | Corrections Issued | CARLOS MATAMOROS |
| Insulation | 7/23/2024 | Partial Approval | CARLOS MATAMOROS |
| Insulation | 7/25/2024 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 8/22/2024 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 8/22/2024 | Approved | CARLOS MATAMOROS |
| Shower Pan | 9/25/2024 | Approved | CARLOS MATAMOROS |
| Gas Test | 9/16/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 9/26/2025 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 9/26/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 9/26/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/1/2026 | Approved | EVAN COOPER |
| Final | 4/1/2026 | Permit Finaled | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/1/2026 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/1/2026 | Approved | EVAN COOPER |