14707 W ORACLE PL 90272

Certificate Information: 14707 W ORACLE PL 90272

Application / Permit
23016-10000-26733
Plan Check / Job No.
B23LA14868
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Interior remodel of (E) SFD. All work per engineer design.
Permit Issued
Issued on 9/6/2023
Issuing Office
Current Status
Permit Finaled on 12/16/2025

Permit Application Status History

Submitted 8/10/2023 APPLICANT
Assigned to Plan Check Engineer 8/10/2023 FARSHAD ALIMOHAMADI
Corrections Issued 8/10/2023 FARSHAD ALIMOHAMADI
Plan Check Approved 8/27/2023 FARSHAD ALIMOHAMADI
Issued 9/6/2023 APPLICANT
Permit Finaled 12/15/2025 TEMISTOCLES CAAL

Permit Application Clearance Information

Grading Pre-Inspection Cleared 8/22/2023 SERGIO VALENZUELA

Contact Information

Contractor Freemodel Inc; Lic. No.: 1066986-B       ,
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: C84559 9163 LEROY STREET      SAN GABRIEL, CA 91775
Engineer Tajvidi,, Seyed Mohammad; Lic. No.: NA84559       ,

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/18/2023 Corrections Issued OGANES TARAKHCHYAN
Special/Order Compliance 9/18/2023 Corrections Issued OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 9/21/2023 Not Ready for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 10/2/2023 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/2/2023 Approved OGANES TARAKHCHYAN
Pre-Inspection 1/25/2024 Partial Inspection ARAM AVEDISIAN
Pre-Inspection 4/19/2024 Partial Inspection ARAM AVEDISIAN
PLUMBING-Rough 5/31/2024 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 6/5/2024 Approved ARAM AVEDISIAN
Insulation 6/13/2024 Corrections Issued CARLOS MATAMOROS
Wood Frame 6/17/2024 Approved ARAM AVEDISIAN
Insulation 6/24/2024 Approved EVAN COOPER
BUILDING-Rough-Frame 7/2/2024 Approved KENNETH NAGLE
Drywall Nailing 7/2/2024 Approved KENNETH NAGLE
Shower Pan 8/5/2024 Approved EVAN COOPER
Interior/Exterior Lathing 9/13/2024 Approved JESUS RODRIGUEZ
Gas Test 8/14/2025 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Final 8/14/2025 Not Ready for Inspection MEL KHACHATOURIAN
Gas Test 8/18/2025 Approved BOBBY KEY
PLUMBING-Final 8/18/2025 Approved BOBBY KEY
ELECTRICAL-Final 9/12/2025 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Final 9/17/2025 Approved TEMISTOCLES CAAL
Final 10/8/2025 Corrections Issued TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Approved TEMISTOCLES CAAL
Smoke Detectors 10/8/2025 Approved TEMISTOCLES CAAL
Final 12/15/2025 Permit Finaled TEMISTOCLES CAAL