633 W 5TH ST 20th floor 90071
Certificate Information: 633 W 5TH ST 20th floor 90071
- Application / Permit
- 23016-10000-26693
- Plan Check / Job No.
- B23LA14843
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Eplan. TENANT IMPROVEMENT WORK ON 10,032 SQ. FT. OF EXISTING OFFICE SPACE. NEW NON-LOAD BEARING WALLS, NEW LIGHTING, NEW FINISHES.
- Permit Issued
- Issued on 9/29/2023
- Issuing Office
- Current Status
- Permit Finaled on 4/11/2024
Permit Application Status History
| Submitted | 8/11/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 8/16/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 9/27/2023 | KEVIN MORALES |
| Issued | 9/29/2023 | APPLICANT |
| Permit Finaled | 4/11/2024 | LUIS CCAMACHO |
Permit Application Clearance Information
| Fire Marshal Fire Life Safety | Cleared | 9/25/2023 | RONILO MULAWIN |
Contact Information
| Architect | Algaze,, Nelson; Lic. No.: NA21090 | , |
| Contractor | Corporate Contractors Inc; Lic. No.: 604407-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 10/25/2023 | Partial Approval | RAMAZANALI ALMASI |
| Insulation | 10/26/2023 | Partial Inspection | JACOB MYERS |
| Insulation | 10/30/2023 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 10/30/2023 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 12/1/2023 | Approved | KATY RAMIREZ |
| Drywall Nailing | 12/5/2023 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 12/14/2023 | Partial Approval | KATY RAMIREZ |
| T-Bar Ceiling | 12/19/2023 | Partial Approval | KATY RAMIREZ |
| Final | 3/7/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 3/7/2024 | Approved | LUIS CCAMACHO |
| Final | 4/9/2024 | Not Ready for Inspection | LUIS CCAMACHO |
| Final | 4/11/2024 | Permit Finaled | LUIS CCAMACHO |