12931 W GREENE AVE 90066
Certificate Information: 12931 W GREENE AVE 90066
- Application / Permit
- 23016-10000-26456
- Plan Check / Job No.
- B23LA14701
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (E) FIRST FLOOR TO REMAIN AS IS. CONVERT SECOND FLOOR (E) ACCESSORY LIVING QUARTERS TO (N) ADU (ACCESSORY DWELLING UNIT) 819SQFT PER STATE LAW NO SQFT ADDED, NO STRUCTURAL WORK
- Permit Issued
- Issued on 8/24/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2023 | KHUONG TRUONG |
| Corrections Issued | 8/8/2023 | KHUONG TRUONG |
| Plan Check Approved | 8/24/2023 | WEIJIAN HUANG |
| Issued | 8/24/2023 | APPLICANT |
| CofO in Progress | 10/18/2023 | RYAN BARNES |
| Permit Finaled | 11/16/2023 | BRUCE TODD |
| CofO Issued | 11/16/2023 | BRUCE TODD |
| Permit Finaled | 11/16/2023 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2023 | DARIN LAM |
| Specific Plan | Cleared | 8/23/2023 | ROBERT SANCHEZ |
| Sewer availability | Cleared | 8/24/2023 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Barboza Jose J V; Lic. No.: 286948-B | 12933 GREEN AVENUE LOS ANGELES, CA 90066 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/21/2023 | Not Ready for Inspection | HERBERT GIRON |
| METHANE-Final | 9/21/2023 | Not Ready for Inspection | HERBERT GIRON |
| METHANE-Rough | 9/21/2023 | Not Ready for Inspection | HERBERT GIRON |
| Smoke Detectors | 9/21/2023 | Not Ready for Inspection | HERBERT GIRON |
| Final | 9/22/2023 | Corrections Issued | ANDREW BEELI |
| BUILDING-Rough-Frame | 10/11/2023 | Not Ready for Inspection | RYAN BARNES |
| Final | 10/11/2023 | Not Ready for Inspection | RYAN BARNES |
| METHANE-Final | 10/11/2023 | Not Ready for Inspection | RYAN BARNES |
| METHANE-Rough | 10/11/2023 | Approved | RYAN BARNES |
| Smoke Detectors | 10/11/2023 | Not Ready for Inspection | RYAN BARNES |
| BUILDING-Rough-Frame | 10/13/2023 | Approved | RYAN BARNES |
| Final | 10/13/2023 | Conditional Approval | RYAN BARNES |
| METHANE-Final | 10/13/2023 | Approved | RYAN BARNES |
| METHANE-Rough | 10/13/2023 | Approved | RYAN BARNES |
| Smoke Detectors | 10/13/2023 | Approved | RYAN BARNES |