2823 S CORNING ST 1-5 90034
Certificate Information: 2823 S CORNING ST 1-5 90034
- Application / Permit
- 23016-10000-26140
- Plan Check / Job No.
- B23LA14534
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERSION OF (E) ATTACHED TWO CAR GARAGE WITHIN A TWO STORY THREE UNIT + 1 GUEST ROOM APARTMENT BUILDING INTO AN ADU PER CA GOVT. CODE 65852.2(e)(1)(C)
- Permit Issued
- Issued on 5/16/2024
- Issuing Office
- Current Status
- CofO Issued on 1/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/10/2023 | SERGIO GUTIERREZ |
| Corrections Issued | 8/15/2023 | SERGIO GUTIERREZ |
| Quality Review Completed | 8/22/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 2/13/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 3/19/2024 | SERGIO GUTIERREZ |
| Issued | 5/16/2024 | APPLICANT |
| CofO in Progress | 12/29/2025 | FARHAD DADBIN |
| Permit Finaled | 1/12/2026 | DAVID TSAU |
| CofO Issued | 1/12/2026 | DAVID TSAU |
| Permit Finaled | 1/12/2026 | DAVID TSAU |
Permit Application Clearance Information
| Green Code | Cleared | 8/25/2023 | Ricardo Ramirez Solis |
| Roof/Waste drainage to street | Cleared | 9/18/2023 | NEIL TUANO |
| Sewer availability | Cleared | 9/18/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2023 | NEIL TUANO |
| Hydrant and Access approval | Cleared | 10/9/2023 | LAVEON RIDER |
| Address approval | Cleared | 11/25/2023 | STEVE MELGAR |
| DAS Clearance | Cleared | 11/29/2023 | Ricardo Ramirez Solis |
| Tenant Habitability Plan | Cleared | 2/23/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Jlg Works; Lic. No.: 974350-B | 5128 WEST 130TH STREET HAWTHORNE, CA 90250 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: NA68149 | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/30/2024 | Approved | FARHAD DADBIN |
| Footing/Foundation/Slab | 2/28/2025 | Approved | AMANUEL BERHE |
| Green Building Rough | 4/11/2025 | Approved | FARHAD DADBIN |
| Wood Frame | 4/11/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 5/19/2025 | Approved | FARHAD DADBIN |
| Wood Frame | 5/19/2025 | Conditional Approval | FARHAD DADBIN |
| Drywall Nailing | 5/28/2025 | Approved | FARHAD DADBIN |
| Final | 10/29/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 10/29/2025 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 10/29/2025 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 10/29/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 10/29/2025 | Approved | FARHAD DADBIN |
| Final | 12/23/2025 | OK to Issue CofO | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 12/23/2025 | Approved | FARHAD DADBIN |