11529 N DRONFIELD AVE 91331

Certificate Information: 11529 N DRONFIELD AVE 91331

Application / Permit
23016-10000-25693
Plan Check / Job No.
B23VN09821
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
eplan. Convert existing 1-story Single Family Dwelling at rear of lot to an Accessory Living Quarters and 12 'x 28' addition per WFPP
Permit Issued
Issued on 7/24/2024
Issuing Office
Current Status
CofO Issued on 12/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2023 APPLICANT
Assigned to Plan Check Engineer 7/26/2023 PRANITA SHAH
Corrections Issued 8/2/2023 PRANITA SHAH
Quality Review Completed 8/17/2023 MICHAEL PEREZ
Plan Check Approved 7/17/2024 PRANITA SHAH
Plan Check Approved 7/24/2024 PRANITA SHAH
Issued 7/24/2024 APPLICANT
CofO in Progress 11/18/2025 MICHEL ABAJAN
Permit Finaled 12/24/2025 RUBEN SALAS
CofO Issued 12/24/2025 RUBEN SALAS
Permit Finaled 12/24/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/11/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/11/2024 CARLOS AGUILERA
ZA Case Cleared 7/11/2024 ROSALINDA MEZA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/29/2024 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 7/30/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/13/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/13/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 6/13/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/25/2025 Approved MICHEL ABAJAN
Insulation 7/2/2025 No Access for Inspection LOUIS ESCOTO
Drywall Nailing 7/9/2025 Approved MICHEL ABAJAN
Underground Mechanical 9/4/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Final 11/17/2025 Approved MICHEL ABAJAN
Final 11/17/2025 OK to Issue CofO MICHEL ABAJAN
Footing/Foundation/Slab 11/17/2025 Approved MICHEL ABAJAN
Green Building Final 11/17/2025 Approved MICHEL ABAJAN
HVAC-Final 11/17/2025 Approved MICHEL ABAJAN
PLUMBING-Final 11/17/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 11/17/2025 Approved MICHEL ABAJAN