12871 W OSBORNE ST 91331
Certificate Information: 12871 W OSBORNE ST 91331
- Application / Permit
- 23016-10000-25532
- Plan Check / Job No.
- B23LA14217
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ATTACHED PATIO COVER ENCLOSURE WITH ADDITION TO ADD BEDROOMS AT REAR OF SFD, REMODEL SFD. ALL WORK DONE PER ENGINEERED DESIGN. NFPA-13D FIRE SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 9/15/2023
- Issuing Office
- Current Status
- CofO Issued on 12/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 8/9/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/15/2023 | APPLICANT |
| Applicant returned to address corrections | 9/11/2023 | MINA HABILI |
| Plan Check Approved | 9/15/2023 | DANIEL SMILEY |
| Issued | 9/15/2023 | APPLICANT |
| CofO in Progress | 11/14/2025 | MICHEL ABAJAN |
| CofO Issued | 12/2/2025 | RUBEN SALAS |
| Permit Finaled | 12/2/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/11/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 9/15/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grandhi,, Venkata Rohit; Lic. No.: C88709 | 7823 BOXWOOD CT HIGHLAND, CA 92346 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/25/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 9/28/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 9/28/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 9/28/2023 | Approved | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 10/4/2023 | Partial Approval | MICHEL ABAJAN |
| Deputy Wood Construction | 10/11/2023 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/17/2023 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/17/2023 | Approved | MICHEL ABAJAN |
| Insulation | 10/19/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/19/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 10/19/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/24/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 11/13/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/24/2024 | No Access for Inspection | MICHEL ABAJAN |
| Final | 1/24/2024 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 1/24/2024 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Rough | 1/24/2024 | No Access for Inspection | MICHEL ABAJAN |
| METHANE-Final | 1/24/2024 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 1/24/2024 | No Access for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/3/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/3/2025 | Approved | MICHEL ABAJAN |
| Final | 3/3/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 3/3/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 3/3/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 3/3/2025 | Approved | MICHEL ABAJAN |
| METHANE-Final | 3/3/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/3/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/3/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 3/3/2025 | Approved | MICHEL ABAJAN |