4213 S 11TH AVE 90008

Certificate Information: 4213 S 11TH AVE 90008

Application / Permit
23016-10000-25475
Plan Check / Job No.
B23LA14192
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
convert exisiting detached garage into adu per State Law, CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/9/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2023 APPLICANT
Assigned to Plan Check Engineer 9/5/2023 AUNG SOE
Corrections Issued 9/12/2023 AUNG SOE
Building Plans Picked Up 9/13/2023 APPLICANT
Plan Check Approved 1/9/2024 SHANGQIN XIE
Issued 1/9/2024 APPLICANT
CofO in Progress 4/30/2026 LUIS CASTRO
Permit Finaled 4/30/2026 DEROLD HAUFF
CofO Issued 4/30/2026 DEROLD HAUFF
Permit Finaled 4/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/30/2023 CHRISTINA BRACO
Sewer availability Cleared 9/30/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 10/23/2023 CHRISTINA BRACO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/20/2024 Approved MICHAEL LEWIS
Pre-Inspection 12/10/2024 Approved BARRY HACHE
Pre-Inspection 1/15/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 1/21/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 1/23/2025 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 1/27/2025 Approved LUIS CASTRO
Sewer 2/5/2025 Partial Approval LUIS CASTRO
Sewer 2/20/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Partial Approval LUIS CASTRO
Footing/Foundation/Slab 2/25/2025 Not Ready for Inspection LUIS CASTRO
Footing/Foundation/Slab 3/4/2025 Approved LUIS CASTRO
ELECTRICAL-Rough 3/6/2025 Corrections Issued LUIS CASTRO
Interior/Exterior Lathing 3/6/2025 No Access for Inspection LUIS CASTRO
PLUMBING-Rough 3/6/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 3/10/2025 Approved LUIS CASTRO
HVAC-Rough 3/10/2025 Approved LUIS CASTRO
PLUMBING-Rough 3/10/2025 Approved LUIS CASTRO
Insulation 4/15/2025 Partial Approval LUIS CASTRO
Interior/Exterior Lathing 4/15/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 4/17/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Approved LUIS CASTRO
Insulation 4/18/2025 Corrections Issued LUIS CASTRO
Drywall Nailing 4/22/2025 Approved ALEX COLIN
ELECTRICAL-Final 12/10/2025 Corrections Issued LUIS CASTRO
PLUMBING-Final 12/10/2025 Approved LUIS CASTRO
ELECTRICAL-Final 3/13/2026 Partial Approval LUIS CASTRO
ELECTRICAL-Final 4/15/2026 Approved LUIS CASTRO
Final 4/15/2026 Corrections Issued LUIS CASTRO
HVAC-Final 4/15/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 4/15/2026 SGSOV Not Required LUIS CASTRO
Service/Power Release 4/15/2026 Not Ready for Inspection LUIS CASTRO
Smoke Detectors 4/15/2026 Approved LUIS CASTRO
Final 4/28/2026 OK to Issue CofO LUIS CASTRO
Service/Power Release 4/28/2026 Approved LUIS CASTRO