4213 S 11TH AVE 90008
Certificate Information: 4213 S 11TH AVE 90008
- Application / Permit
- 23016-10000-25475
- Plan Check / Job No.
- B23LA14192
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- convert exisiting detached garage into adu per State Law, CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/9/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2023 | AUNG SOE |
| Corrections Issued | 9/12/2023 | AUNG SOE |
| Building Plans Picked Up | 9/13/2023 | APPLICANT |
| Plan Check Approved | 1/9/2024 | SHANGQIN XIE |
| Issued | 1/9/2024 | APPLICANT |
| CofO in Progress | 4/30/2026 | LUIS CASTRO |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2023 | CHRISTINA BRACO |
| Sewer availability | Cleared | 9/30/2023 | CHRISTINA BRACO |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2023 | CHRISTINA BRACO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/20/2024 | Approved | MICHAEL LEWIS |
| Pre-Inspection | 12/10/2024 | Approved | BARRY HACHE |
| Pre-Inspection | 1/15/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 1/21/2025 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 1/23/2025 | Corrections Issued | LUIS CASTRO |
| Footing/Foundation/Slab | 1/27/2025 | Approved | LUIS CASTRO |
| Sewer | 2/5/2025 | Partial Approval | LUIS CASTRO |
| Sewer | 2/20/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Partial Approval | LUIS CASTRO |
| Footing/Foundation/Slab | 2/25/2025 | Not Ready for Inspection | LUIS CASTRO |
| Footing/Foundation/Slab | 3/4/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Rough | 3/6/2025 | Corrections Issued | LUIS CASTRO |
| Interior/Exterior Lathing | 3/6/2025 | No Access for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 3/6/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 3/10/2025 | Approved | LUIS CASTRO |
| HVAC-Rough | 3/10/2025 | Approved | LUIS CASTRO |
| PLUMBING-Rough | 3/10/2025 | Approved | LUIS CASTRO |
| Insulation | 4/15/2025 | Partial Approval | LUIS CASTRO |
| Interior/Exterior Lathing | 4/15/2025 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 4/17/2025 | Approved | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Approved | LUIS CASTRO |
| Insulation | 4/18/2025 | Corrections Issued | LUIS CASTRO |
| Drywall Nailing | 4/22/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 12/10/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 12/10/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 3/13/2026 | Partial Approval | LUIS CASTRO |
| ELECTRICAL-Final | 4/15/2026 | Approved | LUIS CASTRO |
| Final | 4/15/2026 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 4/15/2026 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 4/15/2026 | SGSOV Not Required | LUIS CASTRO |
| Service/Power Release | 4/15/2026 | Not Ready for Inspection | LUIS CASTRO |
| Smoke Detectors | 4/15/2026 | Approved | LUIS CASTRO |
| Final | 4/28/2026 | OK to Issue CofO | LUIS CASTRO |
| Service/Power Release | 4/28/2026 | Approved | LUIS CASTRO |