6920 W SUNSET BLVD 90028
Certificate Information: 6920 W SUNSET BLVD 90028
- Application / Permit
- 23016-10000-25212
- Plan Check / Job No.
- B23LA14066
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Automobile Sales - new
- Work Description
- EPLAN: TENANT IMPROVEMENT AND CHANGE OF USE FROM SHOE STORE INTO A NEW CAR DEALERSHIP. TI: EXISTING INTERIOR WALLS, CEILINGS AND LIGHTS TO BE REMOVED. PROPOSED SHOWROOM AND SERVICE AREAS WITH DEMISING WALLS, RESTROOMS AND BREAKROOM, PARTS MEZZANINE & SERVICE BAY EXISTING SITE IMPROVEMENTS TO REMAIN .
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Current Status
- Permit Finaled on 6/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2023 | TSE MING HUANG |
| Corrections Issued | 8/25/2023 | TSE MING HUANG |
| Quality Review Completed | 8/28/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 2/8/2024 | TSE MING HUANG |
| Plan Check Approved | 2/22/2024 | TSE MING HUANG |
| Issued | 2/22/2024 | APPLICANT |
| Permit Finaled | 6/27/2025 | MARTIN TAVITIAN |
Permit Application Clearance Information
| Miscellaneous | Cleared | 10/12/2023 | BRENNEN OBETO |
| ZA Case | Cleared | 10/12/2023 | BRENNEN OBETO |
| ZA Case | Cleared | 10/12/2023 | BRENNEN OBETO |
| Redevelopment Project Area | Cleared | 11/16/2023 | YASMINE BASHIRI |
| Sewer availability | Cleared | 12/11/2023 | JESSICA OPINION |
| Green Code | Cleared | 12/12/2023 | Sarkis Harabedian |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2023 | JESSICA OPINION |
| Low Impact Development (LID) | Cleared | 1/18/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 1/22/2024 | JESSICA OPINION |
| DAS Clearance | Cleared | 2/20/2024 | Sarkis Harabedian |
Contact Information
| Architect | Andresen,, Douglas Duane; Lic. No.: NA14504 | , |
| Contractor | Lsi-Precision Inc; Lic. No.: 736915-B | , |
| Contractor | Sauers Lopez Construction Inc; Lic. No.: 736915-B | , |
| Engineer | Chen,, Jeff Ying-Chih; Lic. No.: S4699 | 17500 REDHILL AVENUE SUITE 240 IRVINE, CA 92614 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/7/2024 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 3/13/2024 | Partial Approval | TIMOTHY POWELL |
| Wood Frame | 3/13/2024 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 3/19/2024 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 3/19/2024 | Not Ready for Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 3/21/2024 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 3/21/2024 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 3/26/2024 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 3/26/2024 | Partial Approval | TIMOTHY POWELL |
| Wood Frame | 3/26/2024 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 4/2/2024 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 4/2/2024 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 4/2/2024 | Partial Approval | EDWIN GREGORYONA |
| Green Building Rough | 4/5/2024 | Not Ready for Inspection | EDWIN GREGORYONA |
| Wood Frame | 4/5/2024 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 4/18/2024 | Partial Approval | TIMOTHY POWELL |
| Structural Steel Frame | 4/25/2024 | Approved | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Interior/Exterior Lathing | 5/3/2024 | Partial Approval | JEROME BLACKWOOD |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Partial Inspection | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 5/13/2024 | Partial Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 5/14/2024 | Partial Approval | RONALD JIMENEZ |
| Drywall Nailing | 5/22/2024 | Partial Inspection | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Partial Approval | TIMOTHY POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 6/26/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 6/26/2024 | Partial Approval | TIMOTHY POWELL |
| Green Building Rough | 8/28/2024 | Not Ready for Inspection | TIMOTHY POWELL |
| Wood Frame | 8/28/2024 | Partial Approval | TIMOTHY POWELL |
| T-Bar Ceiling | 9/4/2024 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 10/18/2024 | Partial Inspection | TIMOTHY POWELL |
| Drywall Nailing | 12/13/2024 | Partial Approval | TIMOTHY POWELL |
| Green Building Final | 6/20/2025 | Partial Inspection | TIMOTHY POWELL |
| Final | 6/27/2025 | Permit Finaled | MARTIN TAVITIAN |
| Green Building Final | 6/27/2025 | Approved | MARTIN TAVITIAN |
| Green Building Rough | 6/27/2025 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 6/27/2025 | Approved | MARTIN TAVITIAN |
| Wood Frame | 6/27/2025 | Approved | MARTIN TAVITIAN |