1344 N HIGHLAND AVE 90028
Certificate Information: 1344 N HIGHLAND AVE 90028
- Application / Permit
- 23016-10000-25205
- Plan Check / Job No.
- B23LA14061
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- EPLAN CHANGE OF USE FROM PORTION OF PRINTING OFFICE at FIRST LEVEL TO RETAIL.
- Permit Issued
- Issued on 10/17/2023
- Issuing Office
- Current Status
- CofO Issued on 3/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2023 | ZAW HAN |
| Corrections Issued | 8/7/2023 | ZAW HAN |
| Applicant returned to address corrections | 9/29/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 10/4/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 10/6/2023 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 10/11/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/17/2023 | ARSALAN SHABESTARI |
| Issued | 10/17/2023 | APPLICANT |
| Permit Finaled | 3/21/2024 | ERNESTO CORRAL |
| CofO Issued | 3/21/2024 | ERNESTO CORRAL |
| Permit Finaled | 3/21/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2023 | AMBER CAMPBELL |
| Sewer availability | Cleared | 8/18/2023 | AMBER CAMPBELL |
| Historic Resource Verification | Cleared | 8/25/2023 | MAX LODER |
| Comm Cor/Mini-Mall | Cleared | 9/6/2023 | DANIEL CORONADO |
| Redevelopment Project Area | Cleared | 9/11/2023 | YASMINE BASHIRI |
| DAS Clearance | Cleared | 10/17/2023 | ANDREW SANTIAGO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/24/2023 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 11/3/2023 | Approved | RONALD JIMENEZ |
| Footing/Foundation/Slab | 11/16/2023 | Partial Approval | RONALD JIMENEZ |
| Pre-Inspection | 11/16/2023 | Approved | RONALD JIMENEZ |
| Footing/Foundation/Slab | 11/17/2023 | Partial Inspection | RONALD JIMENEZ |
| Pre-Inspection | 11/17/2023 | Approved | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Approved | RONALD JIMENEZ |
| Wood Frame | 11/28/2023 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 12/8/2023 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 12/8/2023 | Corrections Issued | RONALD JIMENEZ |
| Drywall Nailing | 12/12/2023 | Approved | RONALD JIMENEZ |
| Insulation | 12/12/2023 | Approved | RONALD JIMENEZ |
| Wood Frame | 12/12/2023 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 1/8/2024 | Approved | RONALD JIMENEZ |
| Final | 1/17/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Not Ready | RONALD JIMENEZ |
| Smoke Detectors | 1/17/2024 | Not Ready for Inspection | RONALD JIMENEZ |
| Final | 3/19/2024 | Conditional Approval | DAVID BURKHEAD |
| SGSOV-Seismic Gas S/O Valve | 3/19/2024 | SGSOV Approved | DAVID BURKHEAD |
| Smoke Detectors | 3/19/2024 | Approved | DAVID BURKHEAD |