1077 E AMOROSO PL 90291
Certificate Information: 1077 E AMOROSO PL 90291
- Application / Permit
- 23016-10000-24961
- Plan Check / Job No.
- B23LA13887
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of (E) 1-story SFD including bathrooms, closets, kitchen, removing and replacing doors and windows
- Permit Issued
- Issued on 8/1/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 1/16/2024
Permit Application Status History
| Submitted | 7/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2023 | MICHAEL LANZONE |
| Corrections Issued | 7/27/2023 | MICHAEL LANZONE |
| Plan Check Approved | 7/31/2023 | MINA HABILI |
| Issued | 8/1/2023 | APPLICANT |
| Permit Finaled | 1/16/2024 | RYAN BARNES |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | J P Builders & Development Inc; Lic. No.: 992192-B | P O BOX 5366 SHERMAN OAKS, CA 91413 |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/8/2023 | Conditional Approval | JOHN MATTILLO |
| BUILDING-Rough-Frame | 8/10/2023 | Not Ready for Inspection | ANDREW BEELI |
| Rough-Elec/Plmb/HVAC | 8/14/2023 | Corrections Issued | RYAN BARNES |
| BUILDING-Rough-Frame | 8/16/2023 | Not Ready for Inspection | RYAN BARNES |
| ELECTRICAL-Rough | 8/16/2023 | Approved | RYAN BARNES |
| PLUMBING-Rough | 8/16/2023 | Approved | RYAN BARNES |
| BUILDING-Rough-Frame | 8/18/2023 | No Access for Inspection | RYAN BARNES |
| Insulation | 8/18/2023 | No Access for Inspection | RYAN BARNES |
| Shower Pan | 8/18/2023 | No Access for Inspection | RYAN BARNES |
| Deputy Wood Construction | 8/21/2023 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 8/28/2023 | No Access for Inspection | RYAN BARNES |
| Drywall Nailing | 8/30/2023 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 8/30/2023 | Approved | RYAN BARNES |
| ELECTRICAL-Final | 12/20/2023 | Approved | RYAN BARNES |
| PLUMBING-Final | 12/20/2023 | Approved | RYAN BARNES |
| Final | 1/16/2024 | Permit Finaled | RYAN BARNES |
| SGSOV-Seismic Gas S/O Valve | 1/16/2024 | SGSOV Approved | RYAN BARNES |
| Smoke Detectors | 1/16/2024 | Approved | RYAN BARNES |