620 W 15TH ST 90731

Certificate Information: 620 W 15TH ST 90731

Application / Permit
23016-10000-24952
Plan Check / Job No.
B23LA13877
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
146 sqft addtion, interior alteration to existing one story single family dewlling ALL WORK DONE PER WFPP
Permit Issued
Issued on 9/28/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2023 APPLICANT
Assigned to Plan Check Engineer 8/4/2023 AUNG SOE
Corrections Issued 8/7/2023 AUNG SOE
Building Plans Picked Up 8/9/2023 APPLICANT
Applicant returned to address corrections 8/22/2023 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/29/2023 KHUONG TRUONG
Plan Check Approved 9/28/2023 JOSEPH RAFOLS
Issued 9/28/2023 APPLICANT
CofO in Progress 5/29/2024 ANSON MAGLASANG
CofO Issued 5/29/2024 ANSON MAGLASANG
Permit Finaled 5/29/2024 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/24/2023 HUGO LOPEZ
Roof/Waste drainage to street Cleared 8/24/2023 HUGO LOPEZ
Sewer availability Cleared 8/24/2023 HUGO LOPEZ
Certificate of Compliance Cleared 8/26/2023 YINGSHI HUANG
Historic Resource Verification Cleared 8/31/2023 MAX LODER
Redevelopment Project Area Cleared 9/1/2023 DAVID URITA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/19/2023 Conditional Approval JAMES CHAVEZ
Footing/Foundation/Slab 12/21/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 12/26/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/16/2024 Not Ready for Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 1/16/2024 Partial Approval JAMES CHAVEZ
Green Building Rough 1/16/2024 Not Ready for Inspection JAMES CHAVEZ
BUILDING-Rough-Frame 1/31/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 1/31/2024 Approved EUGENE CASSIDY
Gas Test 1/31/2024 Approved EUGENE CASSIDY
Green Building Rough 1/31/2024 Approved EUGENE CASSIDY
HVAC-Rough 1/31/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 1/31/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/6/2024 Partial Approval EUGENE CASSIDY
Shower Pan 2/6/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 2/12/2024 Partial Approval EUGENE CASSIDY
Insulation 2/14/2024 Approved ANSON MAGLASANG
Drywall Nailing 2/16/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/3/2024 Approved ANSON MAGLASANG
Final 4/3/2024 Corrections Issued ANSON MAGLASANG
Green Building Final 4/3/2024 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 4/3/2024 SGSOV Approved ANSON MAGLASANG
Smoke Detectors 4/3/2024 Not Ready for Inspection ANSON MAGLASANG
Final 5/29/2024 OK to Issue CofO ANSON MAGLASANG
Smoke Detectors 5/29/2024 Approved ANSON MAGLASANG