1920 N HYPERION AVE 90027
Certificate Information: 1920 N HYPERION AVE 90027
- Application / Permit
- 23016-10000-24848
- Plan Check / Job No.
- B23LA13815
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- *eplan* >>SINGLE OCCUPANCY ACCESSIBLE RESTROOM AND A WHEELCHAIR LIFT FROM THE GROUND LEVEL PARKING DOWN TO THE BASEMENT. >>>EXTERIOR: EAST FACADE/ ENTRY OF THE BUILDING TO ACCOMMODATE THE NEW WHEELCHAIR LIFT. NO CCHANGE OF USE.
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- Current Status
- Permit Finaled on 2/23/2026
Permit Application Status History
| Submitted | 7/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/3/2023 | TSE MING HUANG |
| Corrections Issued | 8/9/2023 | TSE MING HUANG |
| Quality Review Completed | 8/10/2023 | EUGENE BARBEAU |
| Plan Check Approved | 12/8/2023 | TSE MING HUANG |
| Issued | 9/30/2024 | APPLICANT |
| Permit Finaled | 2/19/2026 | SEAN POMISH |
Permit Application Clearance Information
| "Q" conditions | Cleared | 8/11/2023 | YINGSHI HUANG |
| Roof/Waste drainage to street | Cleared | 8/11/2023 | NEIL TUANO |
| Sewer availability | Cleared | 8/11/2023 | NEIL TUANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/17/2023 | NEIL TUANO |
| DAS Clearance | Cleared | 12/7/2023 | Shangqin Xie |
Contact Information
| Architect | King,, Christopher Michael; Lic. No.: NA32261 | , |
| Contractor | Platinum Construction Design; Lic. No.: 928217-B | , |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/27/2024 | No Result Entered | TIMOTHY KEY |
| Pre-Inspection | 2/25/2025 | Partial Inspection | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 2/28/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Insulation | 2/28/2025 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Pre-Inspection | 7/29/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 7/31/2025 | Partial Approval | LUIS CCAMACHO |
| Insulation | 7/31/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 8/12/2025 | Approved | RONALD JIMENEZ |
| Insulation | 8/12/2025 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 8/13/2025 | No Access for Inspection | RONALD JIMENEZ |
| Insulation | 8/13/2025 | No Access for Inspection | RONALD JIMENEZ |
| Final | 1/26/2026 | Not Ready for Inspection | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 1/26/2026 | SGSOV Not Ready | RONALD JIMENEZ |
| Smoke Detectors | 1/26/2026 | Approved | RONALD JIMENEZ |
| Special/Order Compliance | 1/26/2026 | Approved | SEAN GRIFFITH |
| Final | 2/19/2026 | Permit Finaled | SEAN POMISH |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Approved | SEAN POMISH |