11234-11236 N DRONFIELD AVE 91331

Certificate Information: 11234-11236 N DRONFIELD AVE 91331

Application / Permit
23016-10000-24713
Plan Check / Job No.
B23VN08296
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Convert portion of the (E) attached garage and storage room of the single family dweling to a JADU remove portion of the garage to provide 10' passageway. per CA Govt' Code Section 65852.2(e)(1)(A) and 65852.22
Permit Issued
Issued on 3/29/2024
Issuing Office
Current Status
Issued on 3/29/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/22/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 SAM CHANG
Corrections Issued 7/27/2023 SAM CHANG
Quality Review Completed 7/31/2023 EUGENE BARBEAU
Applicant returned to address corrections 9/7/2023 SAM CHANG
Applicant returned to address corrections 9/12/2023 SAM CHANG
Applicant returned to address corrections 2/7/2024 SAM CHANG
Applicant returned to address corrections 3/6/2024 SAM CHANG
Plan Check Approved 3/27/2024 SAM CHANG
Issued 3/29/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/7/2023 TAL SHEMEN
Sewer availability Cleared 8/7/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 8/9/2023 TAL SHEMEN
Grading Pre-Inspection Cleared 2/7/2024 SAM CHANG

Contact Information

Contractor Owner-Builder       ,
Engineer Shahbaz,, Shant Pierre; Lic. No.: C93079 15445 VENTURA BLVD #63      SHERMAN OAKS, CA 91403

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/7/2025 Partial Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 1/24/2026 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 1/24/2026 Partial Approval CHRISTOPHER ROJAS
Gas Test 4/20/2026 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 4/20/2026 Partial Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/28/2026 Approved MISAEL ESPARZA
ELECTRICAL-Rough 6/10/2026 Approved MICHEL ABAJAN
HVAC-Rough 6/10/2026 Approved MICHEL ABAJAN
PLUMBING-Rough 6/10/2026 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/22/2026 Approved MICHEL ABAJAN
Green Building Rough 6/22/2026 Approved MICHEL ABAJAN