422 S DENSLOW AVE 90049

Certificate Information: 422 S DENSLOW AVE 90049

Application / Permit
23016-10000-24686
Plan Check / Job No.
B23LA13734
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Interior Remodel to (E) Single Family Dwelling to reconfigure interior floor plan layout with major structural alterations including demolish load-bearing walls . Exterior alterations including changes to exterior window and door openings . All work per engineered plans.
Permit Issued
Issued on 8/29/2023
Issuing Office
Current Status
Permit Finaled on 1/24/2025

Permit Application Status History

Submitted 7/26/2023 APPLICANT
Assigned to Plan Check Engineer 8/2/2023 MICHAEL LANZONE
Corrections Issued 8/3/2023 MICHAEL LANZONE
Plan Check Approved 8/24/2023 GEORGE ALVAREZ
No Progress 8/24/2023 GEORGE ALVAREZ
Plan Check Approved 8/24/2023 GEORGE ALVAREZ
Issued 8/29/2023 APPLICANT
Permit Finaled 1/23/2025 CARLOS MATAMOROS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/16/2023 KIMBERLY HERNANDEZ
Sewer availability Cleared 8/16/2023 KIMBERLY HERNANDEZ
Grading Pre-Inspection Cleared 8/18/2023 ROBERT HUGHES

Contact Information

Architect Fallen,, Keith; Lic. No.: C34528 1059 VAN BUREN AVENUE      VENICE, CA 90291
Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Naylor Kevin Construction Inc; Lic. No.: 1001762-B       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/9/2023 Approved CHRISTOPHER WILSON
Pre-Inspection 1/26/2024 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 1/29/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Not Ready for Inspection CARLOS MATAMOROS
Deputy Wood Construction 4/22/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Not Ready for Inspection CARLOS MATAMOROS
Interior/Exterior Lathing 5/3/2024 Partial Approval STEPHANIE SWANSON
Wood Frame 5/10/2024 Partial Approval CARLOS MATAMOROS
Insulation 5/17/2024 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Approved CARLOS MATAMOROS
Wood Frame 5/21/2024 Approved CARLOS MATAMOROS
Drywall Nailing 5/28/2024 Approved CARLOS MATAMOROS
Pre-Inspection 6/24/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 7/2/2024 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 8/13/2024 Approved CARLOS MATAMOROS
Special/Order Compliance 8/28/2024 Approved CARLOS MATAMOROS
Insulation 9/19/2024 Not Ready for Inspection SEAN HAUPT
Final 12/12/2024 Partial Approval CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 12/12/2024 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 12/12/2024 Approved CHRISTOPHER WILSON
Final 12/20/2024 Partial Approval CARLOS MATAMOROS
Final 1/23/2025 Permit Finaled CARLOS MATAMOROS