5898 W 75TH ST 90045

Certificate Information: 5898 W 75TH ST 90045

Application / Permit
23016-10000-24643
Plan Check / Job No.
B23LA13699
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E) GARAGE CONVERSION TO ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/29/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/25/2023 APPLICANT
Assigned to Plan Check Engineer 7/25/2023 DANIEL SANJUAN
Plan Check Approved 8/22/2023 SHANGQIN XIE
Issued 9/29/2023 APPLICANT
CofO in Progress 6/18/2024 TEMISTOCLES CAAL
Permit Finaled 6/24/2024 DANIEL ORRANTE
CofO Issued 6/24/2024 DANIEL ORRANTE
Permit Finaled 6/24/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/7/2023 JASON NG
Roof/Waste drainage to street Cleared 8/7/2023 JASON NG
Sewer availability Cleared 8/7/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 8/8/2023 JASON NG
Specific Plan Cleared 8/9/2023 ROBERT SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/29/2023 Approved BOBBY KEY
PLUMBING-Rough 11/29/2023 Not Ready for Inspection BOBBY KEY
Special/Order Compliance 11/29/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 2/12/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Approved BOBBY KEY
HVAC-Rough 2/12/2024 Corrections Issued BOBBY KEY
PLUMBING-Rough 2/12/2024 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 2/15/2024 Conditional Approval BOBBY KEY
Green Building Rough 2/15/2024 Approved BOBBY KEY
HVAC-Rough 2/15/2024 Approved BOBBY KEY
Interior/Exterior Lathing 2/15/2024 Partial Approval BOBBY KEY
Insulation 2/23/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/28/2024 Approved TEMISTOCLES CAAL
Drywall Nailing 2/28/2024 Approved TEMISTOCLES CAAL
Interior/Exterior Lathing 2/28/2024 Approved TEMISTOCLES CAAL
MERV13>=Rough 2/28/2024 Approved TEMISTOCLES CAAL
Sewer 4/1/2024 Approved BOBBY KEY
ELECTRICAL-Final 6/11/2024 Corrections Issued BOBBY KEY
Final 6/11/2024 Corrections Issued BOBBY KEY
Green Building Final 6/11/2024 Approved BOBBY KEY
HVAC-Final 6/11/2024 Corrections Issued BOBBY KEY
MERV13>=Final 6/11/2024 Approved BOBBY KEY
PLUMBING-Final 6/11/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 6/11/2024 Approved BOBBY KEY
ELECTRICAL-Final 6/13/2024 Not Ready for Inspection BOBBY KEY
HVAC-Final 6/13/2024 Approved BOBBY KEY
ELECTRICAL-Final 6/14/2024 Corrections Issued TEMISTOCLES CAAL
Final 6/14/2024 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 6/14/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 6/14/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 6/17/2024 Approved TEMISTOCLES CAAL
Final 6/17/2024 OK to Issue CofO TEMISTOCLES CAAL