2408 N HARWOOD ST 90031
Certificate Information: 2408 N HARWOOD ST 90031
- Application / Permit
- 23016-10000-24558
- Plan Check / Job No.
- B23LA13644
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: REMOVE PORTION OF (E) DETACHED GARAGE AND CONVERT TO A (N) ADU TO BE PART OF AN (E) ADU INTO A (N) IRREGULAR SHAPED DETACHED 37'-6" x 27'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) AND (d). ALL WORK PER DESIGN. SEE COMMENTS
- Permit Issued
- Issued on 11/27/2023
- Issuing Office
- Current Status
- CofO Issued on 10/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2023 | ALFRED RAMIREZ |
| Corrections Issued | 8/3/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 11/23/2023 | PINANK PATEL |
| Issued | 11/27/2023 | APPLICANT |
| CofO in Progress | 10/2/2024 | THOMAS LOGRASSO |
| Permit Finaled | 10/15/2024 | RUBEN SALAS |
| CofO Issued | 10/15/2024 | RUBEN SALAS |
| Permit Finaled | 10/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 8/16/2023 | SPENCER WEJROWSKI |
| Construction within easement | Cleared | 11/18/2023 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/22/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 5/24/2024 | Partial Approval | SCOTT FINNILA |
| Special/Order Compliance | 5/24/2024 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/31/2024 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 6/13/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 6/17/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/11/2024 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 7/17/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/1/2024 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 8/1/2024 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 8/1/2024 | Not Ready for Inspection | SCOTT FINNILA |
| Insulation | 8/1/2024 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 8/6/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/6/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 8/6/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/6/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/12/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2024 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 8/12/2024 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/12/2024 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/19/2024 | Approved | WILLIAM SIERRA |
| Insulation | 8/19/2024 | Approved | WILLIAM SIERRA |
| Interior/Exterior Lathing | 8/19/2024 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 8/22/2024 | Approved | ANTHONY RAMOS |
| ELECTRICAL-Final | 9/24/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 9/24/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 9/24/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 9/24/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 9/24/2024 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 9/24/2024 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/24/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 10/1/2024 | OK to Issue CofO | THOMAS LOGRASSO |
| Green Building Final | 10/1/2024 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 10/1/2024 | Approved | THOMAS LOGRASSO |