6922 W 85TH PL 90045
Certificate Information: 6922 W 85TH PL 90045
- Application / Permit
- 23016-10000-24486
- Plan Check / Job No.
- B23LA13594
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan* Convert existing garage into Detached ADU per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2023 | JASON JANGADA |
| Corrections Issued | 8/1/2023 | JASON JANGADA |
| Applicant returned to address corrections | 9/5/2023 | EDWIN ESPIN |
| Applicant returned to address corrections | 9/22/2023 | DAVID CASTILLO |
| Plan Check Approved | 9/25/2023 | DAVID CASTILLO |
| Issued | 9/26/2023 | APPLICANT |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
| CofO Issued | 4/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2023 | MSTAFA AL-MSARI |
| Specific Plan | Cleared | 8/16/2023 | ROBERT SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2023 | MSTAFA AL-MSARI |
| Sewer availability | Cleared | 8/24/2023 | MSTAFA AL-MSARI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/24/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 10/24/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 10/27/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 1/24/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 1/24/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/24/2024 | Conditional Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 1/31/2024 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 1/31/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/31/2024 | Approved | BOBBY KEY |
| Insulation | 2/6/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 2/20/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/20/2024 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 2/26/2024 | Partial Approval | HERBERT GIRON |
| Shower Pan | 2/26/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/26/2024 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 11/26/2024 | Corrections Issued | DAVID FEILER |
| Final | 11/26/2024 | Corrections Issued | DAVID FEILER |
| Green Building Final | 11/26/2024 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 11/26/2024 | Approved | DAVID FEILER |
| HVAC-Final | 11/26/2024 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 11/26/2024 | Corrections Issued | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 11/26/2024 | SGSOV Not Ready | DAVID FEILER |
| Smoke Detectors | 11/26/2024 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 1/28/2026 | Corrections Issued | JESUS PINEDA |
| Final | 1/28/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 1/28/2026 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 1/28/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 1/28/2026 | Approved | JESUS PINEDA |
| PLUMBING-Final | 1/28/2026 | Corrections Issued | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 1/28/2026 | Not Required | JESUS PINEDA |
| Smoke Detectors | 1/28/2026 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 3/25/2026 | Approved | ANTHONY EGSON |
| Final | 3/25/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 3/25/2026 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 3/25/2026 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 4/10/2026 | Approved | RUBEN RIVAS |
| Final | 4/10/2026 | Partial Approval | RUBEN RIVAS |
| Green Building Final | 4/10/2026 | Approved | RUBEN RIVAS |
| HVAC-Final | 4/10/2026 | Approved | RUBEN RIVAS |
| PLUMBING-Final | 4/10/2026 | Approved | RUBEN RIVAS |