6922 W 85TH PL 90045

Certificate Information: 6922 W 85TH PL 90045

Application / Permit
23016-10000-24486
Plan Check / Job No.
B23LA13594
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan* Convert existing garage into Detached ADU per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 9/26/2023
Issuing Office
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/24/2023 APPLICANT
Assigned to Plan Check Engineer 8/1/2023 JASON JANGADA
Corrections Issued 8/1/2023 JASON JANGADA
Applicant returned to address corrections 9/5/2023 EDWIN ESPIN
Applicant returned to address corrections 9/22/2023 DAVID CASTILLO
Plan Check Approved 9/25/2023 DAVID CASTILLO
Issued 9/26/2023 APPLICANT
Permit Finaled 4/23/2026 RICHARD STEINBACH
CofO Issued 4/23/2026 RICHARD STEINBACH
Permit Finaled 4/23/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/12/2023 MSTAFA AL-MSARI
Specific Plan Cleared 8/16/2023 ROBERT SANCHEZ
Eng Process Fee Ord 176,300 Cleared 8/24/2023 MSTAFA AL-MSARI
Sewer availability Cleared 8/24/2023 MSTAFA AL-MSARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/24/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 10/24/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 10/27/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/8/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Approved BOBBY KEY
ELECTRICAL-Rough 1/24/2024 Approved BOBBY KEY
HVAC-Rough 1/24/2024 Corrections Issued BOBBY KEY
PLUMBING-Rough 1/24/2024 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 1/31/2024 Conditional Approval BOBBY KEY
HVAC-Rough 1/31/2024 Approved BOBBY KEY
PLUMBING-Rough 1/31/2024 Approved BOBBY KEY
Insulation 2/6/2024 Approved BOBBY KEY
Drywall Nailing 2/20/2024 Approved BOBBY KEY
Interior/Exterior Lathing 2/20/2024 Not Ready for Inspection BOBBY KEY
Interior/Exterior Lathing 2/26/2024 Partial Approval HERBERT GIRON
Shower Pan 2/26/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 11/26/2024 Approved DAVID FEILER
ELECTRICAL-Final 11/26/2024 Corrections Issued DAVID FEILER
Final 11/26/2024 Corrections Issued DAVID FEILER
Green Building Final 11/26/2024 Not Ready for Inspection DAVID FEILER
Green Building Rough 11/26/2024 Approved DAVID FEILER
HVAC-Final 11/26/2024 Corrections Issued DAVID FEILER
PLUMBING-Final 11/26/2024 Corrections Issued DAVID FEILER
SGSOV-Seismic Gas S/O Valve 11/26/2024 SGSOV Not Ready DAVID FEILER
Smoke Detectors 11/26/2024 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Final 1/28/2026 Corrections Issued JESUS PINEDA
Final 1/28/2026 Corrections Issued JESUS PINEDA
Green Building Final 1/28/2026 Corrections Issued JESUS PINEDA
HVAC-Final 1/28/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 1/28/2026 Approved JESUS PINEDA
PLUMBING-Final 1/28/2026 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Approved JESUS PINEDA
Service/Power Release 1/28/2026 Not Required JESUS PINEDA
Smoke Detectors 1/28/2026 Approved JESUS PINEDA
ELECTRICAL-Final 3/25/2026 Approved ANTHONY EGSON
Final 3/25/2026 Not Ready for Inspection ANTHONY EGSON
Green Building Final 3/25/2026 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 3/25/2026 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 4/10/2026 Approved RUBEN RIVAS
Final 4/10/2026 Partial Approval RUBEN RIVAS
Green Building Final 4/10/2026 Approved RUBEN RIVAS
HVAC-Final 4/10/2026 Approved RUBEN RIVAS
PLUMBING-Final 4/10/2026 Approved RUBEN RIVAS